Southside Extension (South Lansing Pathway

Start Date: May 5, 2014
Expected Completion: December 1, 2014

Over the weekend, the pathway was paved from Washington to Hughes and from Davis Park to Wise. Bollards are currently being installed along the pathway, sign installation will begin in the next couple weeks and the contractor is working on constructing the last portion of the pathway from Wise road to Waverly Road. 
Southside Extension Project Page

Moores River Drive Project

Mt. Hope Avenue to Waverly Road

Start Date: April 7, 2014
Expected Completion: October 2014

The contractor has installed benches and bike racks. The pathway is scheduled for paving this week with remaining curb and sidewalk installation to be completed afterward. 
Moores River Drive Project Page

Crack Sealing

Pavement crack sealing has started within the City of Lansing and will occur throughout the City for the next few weeks, as long as weather permits. The City plans to spend $250,000 on crack sealing local and major streets. 

Crack sealing is performed on pavement that is 3-5 years old and prevents water from getting under the pavement, which can cause pavement failures and pot holes. Crack sealing provides the best protection of the road system for the least amount of money. 

Crack sealing will cause only slight traffic disruptions. The street will be available within minutes of the crack sealing being applied. 

Sewer Siphon #11 Replacement Project

Start Date: May 12, 2014
Expected Completion: November 2014 

The contractor is working in E. Elm Street on the north side of the Red Cedar River to complete construction of the new section of large diameter sewer. They are also completing work on the new cast-in-place concrete structures (large "manholes") that allow access to the newly constructed sewer siphon. Riverbank restoration is also underway; after which, restoration of the roadway, river trail and parkway will begin.

The Beech Street Bridge and the block of E. Elm Street north of the bridge will remain closed to all traffic until completion of the project in November.  Progress updates will be provided in this newsletter.
Sewer Siphon #11 Project Page

2014 Lansing Recycling Fun Facts Video

Together we have made a difference by recycling glass, paper, plastic, cardboard, aluminum and metal! Way to go Lansing Citizens! 

Facebook
Facebook
Twitter
Twitter
Website
Website
Copyright © 2014 City of Lansing Public Service Department, All rights reserved.


unsubscribe from this list    update subscription preferences 

Email Marketing Powered by Mailchimp