20th to 17th
Water work:
Water work from 19th-south of 20th St anticipated completion week of 12/1.
Side-street lane restrictions due to water work:
- 20th, one lane of eastbound and westbound traffic between Main and Walnut
Track work:
Track work preparation underway on the east side of Main from 18th-17th Streets. Temporary side street closures will occur.
Systems work:
- Traffic signal work at Main St and 19th St. Various lane drops occur throughout the week. Anticipate completion 12/5.
|
|