Maintenance Report
Slip Bight
Actions from the Jacobs Report have commenced with pile banding, replacement of joists on Jetty 3 , and replacing decking boards. We are awaiting the arrival of toe-capping materials which has been delayed because of a production issue with the supplier. Jetty 5 will undergo a clean up of the concrete pontoon surfaces and repaint red edging and berth numbers.
Chinaman's Creek
Pile caps have been ordered and are due to arrive any day now. These will be installed with banding straps prior to peak period.
Metung Marina
All outstanding defect items have now been repaired including the access gate lock over-ride. Upgrade of the boat launching ramp is scheduled for completion in December The hardstand hoist motor has been replaced and the fencing is scheduled for refurbishment. Competency training for the hoist was conducted on Friday 10 Nov and Sat 11 Nov.
|