Access to Headington: Travel Bulletin
10/03/2017

The Slade

 
We are nearly ready to switch into the next phase of The Slade on the other side of the road.
 
We are currently surfacing the final section on the northbound side of The Slade between Hollow Way and Peat Moors and will be looking to move to the next phase this weekend.
 
The next phase will see us working on the southbound side of The Slade where Wood Farm Road is located. We will be starting at the mini roundabout at Hollow Way and working our way up to Wood Farm Road and then up to Old Road in the final phase. During this time the footpath will be closed and pedestrians will be diverted across onto the newly constructed footpath on the other side of the road. Traffic will continue to be under two-way narrow lanes.
 
We expect this work to be complete mid-December.

Churchill Drive/Old Road

 
The work at the junction of Churchill Drive and Old Road began last week and we have already completed phase one and we’ve just begun phase two.
 
The work consists of installing permanent traffic lights at the junction to help ease the flow during peak times, in and out of the Churchill Hospital site. We are currently removing the existing kerbs and realigning the footpath whilst installing cables under the carriageway for the new traffic lights. We will also be improving the existing cycleway around the junction.
 
Whilst construction is taking place, there are temporary traffic lights in place which are being manually controlled. Churchill Drive is access only and traffic is being diverted via Roosevelt Drive to exit the site.
 
Once the work to the junction is complete, we will then begin work to the junction of Churchill Drive and Roosevelt Drive. This is a small amount of work that involves installing new bus gate. Traffic will also be controlled under temporary traffic lights.
 
This work is scheduled to be complete mid-December.
 
Headley Way/Cherwell Drive
 
This work is currently scheduled to start January 2018. More information to follow in the coming weeks.
 

Like staying up to date?


YourOxfordshire is Oxfordshire County Council’s monthly newsletter, full of great ideas for things to do across the county
Sign up here
Copyright © 2017 Oxfordshire County Council, All rights reserved.


unsubscribe from this list    update subscription preferences