A new Pilot deployment date of December 2017 was just announced by the Central team, allowing for additional stabilization and testing prior to go-live. As a result, a new Deployment 1 (D1) date of June 2018 was proposed for all D1 locations. Potential impacts to UC Davis were discussed in the Steering Committee meeting this week. Special considerations and recommendations will be presented to the D1 Steering Committee.
The Program Management office continues to work with the Central Team and other D1 locations to identify potential risks and close remaining issues. D1 activities are currently focused on Future State Process Designs (FSPDs), data conversion design, configuration information gathering, and data delivery design for downstream systems. Ongoing activities include continued development of the PayPATH solution, conversion design sessions, configuration information gathering, interface development and uploads to the data warehouse.
|