Updates for the Week of March 12, 2017
Crews with Sundt-Davila Joint Venture continue excavation at the tunnel inlet to prepare for the construction of new channel walls and fountains. Storm drain system installation also continues. Utility relocation on Nueva Street will be completed this week and the road will reopen before the week of March 19.
Construction Tour
On Friday, March 31, the San Antonio River Authority will offer a public construction tour of the San Pedro Creek Improvements Project. Participants will meet at 10 a.m. at the Christopher Columbus Italian Society at 201 Piazza Italia. Participants will be provided with safety vests and glasses and a hard hat. Please wear closed-toed shoes and long pants.
To sign up for the tour, visit the San Pedro Creek website.
|