28 July 2017

Link Road
 
It’s still all-go for the Harwell Link Road team with more progress being made since our last update.
 
The team are currently carrying out lining work for the water attenuation  ponds and plans have been agreed for high-voltage line diversions to take place in late-September.
 
South Roundabout:
 
The binder level of tarmac is now complete on all of the roundabout with the subsequent and final layer of wearing course set to be laid in September.
 
Vehicle restraint systems have been installed and traffic is now running on the south side of the roundabout.
 
On the footpaths one section will have its last section of binder layer laid in early August. The wearing course for the footpaths is due to be laid in September
 
Putting up the street lighting should start in early August and be completed by mid-August.
 
 
North Roundabout
 
The team are currently building the gabion wall on north side of roundabout and the south side drainage installation and service duct installation is in progress.
 
Tactile paving is being installed at he crossing points.
 
Kerbs are now complete on the south side so that tarmac can be laid soon. Pedestrians will be diverted to the new footpath area which runs around the south side of the roundabout, this frees up the road to enable us to continue with the works in the north.
 

Like staying up to date?


YourOxfordshire is Oxfordshire County Council’s monthly newsletter, full of great ideas for things to do across the county
Sign up here
Copyright © 2017 Oxfordshire County Council, All rights reserved.


unsubscribe from this list    update subscription preferences