Frank & Harding Street Project Update

Neighbors,
Here is an update on the East Mordecai water & sewer project:

Progress so far:
💧The new sewer main on Frank Street has been completed.
💧The new water main on Frank Street will be completed this coming Monday
💧The existing water & sewer mains in this corridor are very old. This caused some delays in June/July as elevations on existing service lines caused slow production.
💧The additional sidewalk and paving work near the intersection of Brookside Drive and Frank Street is complete.

Upcoming work:
💧The contractor anticipates connecting the new Frank Street water main to the water main in Wake Forest Road on Monday, August 21.
💧Water and sewer service transitions will begin next week. Customers will be notified at least 48 hours prior to a service outage. (or whatever the appropriate notification period is)
💧Final Restoration + Asphalt paving on Frank Street from Norris Street to Wake Forest Road
💧The contractor anticipates being complete with Frank Street on 8/30/17, due to unforeseen delays experienced in June/July. From there, they will transition to Harding Street.

As always, please feel free to reach out with any questions or concerns you may have; and we appreciate everyone’s cooperation with us during construction.

-Regards

Louis Bennett
Project Engineer II
City of Raleigh Public Utilities Department
Phone (919) 996-3504
Fax (919) 996-7567
Louis.Bennett@raleighnc.gov
Mordecai CAC 412 Harding Street Raleigh, NC 27604 USA
Unsubscribe
Email Marketing Powered by Mailchimp