Peter Courtney Minto Island Bridge Update, September 2016

Construction activity will occur between 7 a.m - 4 p.m. Monday - Friday.

Construction Activities:
  • Installation of benches and a bike rack along the newly paved paths at Minto- Brown Park 
  • Shoulder rock placement along the newly paved paths 
  • Construction of additional concrete paths adjacent to and around the Eco-Earth Globe
  • Irrigation work continues
  • Setting of the pre-cast deck panels for the permanent structure will begin this month 
  • Installation of suspension rods connecting the deck with the arches to follow in October 
Note:  All activities are subject to change.

For questions related to construction, please contact Aaron Kimsey at 503.588.6211 or akimsey@cityofsalem.net . For questions related to Park impacts, please call 503.588.6336.

To  see live images of the construction site, please refer to www.cityofsalem.net/MintoBridge.
   
Share Minto News - Subscribe
City of Salem   Copyright © 2016 City of Salem, All rights reserved.


unsubscribe from this list           update subscription preferences 

Email Marketing Powered by Mailchimp  
City of Salem | Disclaimer | Non-Discrimination | ADA Accommodation | Human Rights & Relations