Peter Courtney Minto Island Bridge arches September 2016.
Peter Courtney Minto Island Bridge Update, September 2016
Construction activity will occur between 7 a.m - 4 p.m. Monday - Friday.
Construction Activities:
Installation of benches and a bike rack along the newly paved paths at Minto- Brown Park
Shoulder rock placement along the newly paved paths
Construction of additional concrete paths adjacent to and around the Eco-Earth Globe
Irrigation work continues
Setting of the pre-cast deck panels for the permanent structure will begin this month
Installation of suspension rods connecting the deck with the arches to follow in October
Note: All activities are subject to change.
For questions related to construction, please contact Aaron Kimsey at 503.588.6211 or akimsey@cityofsalem.net . For questions related to Park impacts, please call 503.588.6336.