Copy
View this email in your browser

Field Work Has Begun!

What's happening?
In preparation for the construction of the six-mile Phase II Extension, VTA needs to know more about the soil and the location for utilities in the path of the future project.  This information helps us advance the design and engineering of the BART tunnel, station, and other facilities and avoid project delays once construction begins.   
 
These field investigations started in late September and will continue through the middle of 2019. The subsurface exploration, utility investigations, and geotechnical borings will take place on surface streets, private property, and occasionally on sidewalks as crews work to assess conditions underground.  All working areas will be restored and reopened at the end of each working day, and no weekend work is anticipated.

What type of work is being done?
Geotechnical investigations provide important details about the soil underground and involve drilling and extracting soil samples to test. A truck-mounted drilling rig drills small diameter holes about the size of a soda can up to 150 feet deep to extract soil and groundwater samples.

Utility investigations reveal the precise locations of underground utilities such as water, power, communications, and sewer lines, which are typically located less than six feet down from the surface. A truck-mounted, high-powered vacuum safely removes a small amount of soil around each utility. A surveyor notes the exact location and then the small hole is backfilled. The pavement is replaced and the crew moves to the next location.

How will we find out about this work?
VTA staff has been out in the field to inform stakeholders about the work and will continue to do so two weeks and 72 hours before field work begins. You can also see the current construction notices at http://www.vta.org/bart/construction
 
Getting to know Phase II
The Phase II project is six miles of track that will serve tens of thousands of passengers when complete. We’ve broken up the alignment into nine project areas to better identify specific work that will take place along the corridor. As planning continues for the project, we'll refer to each area by name. Upcoming field work can be below. 
East Portal Area
Anticipated Start Date: Week of 11/19
Locations: On N Marburg Way, Marburg Way, Destino Circle, and Las Plumas Ave
Traffic Impact: At least one lane of traffic will be open at all times where the work is being performed. Work area will be restored once work is complete each day.
Duration of Work: Up to 3 weeks
 
Alum Rock/28th Street Station Area
Anticipated Start Date: Week of 11/13
Locations: On S 22nd St, N 25th St, N 27th St, N 30th St and Five Wounds Ln
Traffic Impact: At least one lane of traffic will be open at all times where the work is being performed. Some parking will be unavailable. Work area will be restored once work is complete each day.
Duration of Work: Up to 6 weeks
13th Street Ventilation Facility Area
Start Date: Week of 10/22
Locations: On S 10th St
Traffic Impact: At least one lane of traffic will be open at all times where the work is being performed. Portions of the sidewalk will be closed. Work area will be restored once work is complete each day.
Duration of Work: Up to 1 week
Downtown San José Station Area
Anticipated Start Date: January 2019
Locations: On E Santa Clara St and on N 3rd St
Traffic Impact: At least one lane of traffic will be open at all times where the work is being performed. Portions of the sidewalk will be closed. Work area will be restored once work is complete each day.
Duration of Work: Up to 1 week
Diridon Station Area
Start Date: Week of 10/9
Locations: On various streets and parking lots bounded by SR-87, W Santa Clara St, Bush St, and Park Ave as well as on Stockton Ave
Traffic Impact: At least one lane of traffic will be open at all times where the work is being performed. Portions of sidewalks on W Santa Clara St, S Montgomery St, Cahill St, and White St will be closed. Work area will be restored once work is complete each day.
Duration of Work: Through January 2019
Stockton Ventilation Facility Area
Anticipated Start Date: Week of 11/13
Locations: On Stockton Ave
Traffic Impact:  At least one lane of traffic will be open at all times where the work is being performed. Portions of the sidewalk and bike lane will be closed. Work area will be restored once work is complete each day.
Duration of Work: Up to 4 weeks
West Portal Area
Start Date: Week of 10/22
Locations: On Stockton Ave, Newhall Dr and Newhall St
Traffic Impact: At least one lane of traffic will be open at all times where the work is being performed. Portions of sidewalk will be closed. Work area will be restored once work is complete each day.
Duration of Work: Up to 7 weeks
Newhall Maintenance Facility Area
Start Date: Week of 10/22
Locations: On the Newhall property east of the train tracks
Traffic Impact: Work area will be restored once work is complete each day.
Duration of Work: Up to 7 days
Santa Clara Station Area
Anticipated Start Date: Week of 12/3
Locations: On Brokaw Rd
Traffic Impact: At least one lane of traffic will be open at all times where the work is being performed. Portions of the sidewalk will be closed. Work area will be restored once work is complete each day.
Duration of Work: Up to 1 week
Have a question for us about Phase II? 
 Visit www.vta.org/bart or email us vtabart@vta.org
Forward
Share
Share

VTA Community Outreach

Follow
Follow
Website
Email
Copyright © 2018 Valley Transportation Authority, All rights reserved.


Want to change how you receive these emails?
You can update your preferences or unsubscribe from this list.