Copy
Thanks for being part of the DLH community!

Runway 9/27 Reconstruction: Phase 3
Duluth International Airport (DLH)

Project Newsletter #14

 

Introduction

This is the 14th weekly newsletter for Phase 3 of the Runway 9/27 Reconstruction project at the Duluth International Airport (DLH).  The purpose of the weekly newsletters will be to provide updates throughout the project regarding construction impacts, runway closures, temporary runway conditions, and other information as needed. Earlier versions of the newsletters will be made available upon request. At any time, you may request a construction update by contacting the project contacts listed in this newsletter.

 

Runway 9/27 Construction Progress

As of early this week, all concrete paving work has been completed for the multi-year effort to reconstruct Runway 9/27. Additionally, all of the concrete paving work on the Phase 3 portions of Runway 3/21, and the new Taxiway A5, have been completed. Yesterday, the bituminous paving of the shoulders began, and will continue through most of next week. Other work items that have been taking place include joint sealing, electrical installations, and grading.

Aerial photo showing concrete paving at the east end of the project (taken last week):
First day of bituminous shoulder paving:

 

Runway/Taxiway Operations - Phase 3C

Phase 3C is currently underway, and Runway 9/27 is operating in the displaced condition with over 7,000' available. Runway closures consist of Runway 3/21. Taxiway closures consist of Taxiway A5, Taxiway E1, and Taxiway C north of Taxiway A.

 For immediate information on the current airfield status, always check current NOTAM's before you fly.


Next Week Preview: August 19th - August 24th

Next week, the following work items are expected to take place: bituminous paving of the shoulders and blast pad, joint widening/sealing, electrical installations, and the installation of the MALSR threshold bar. 


Schedule Updates

The contractor's schedule is currently tracking to be generally on schedule. Depending on weather or unforeseen conditions, the sub-phases are as follows:

Phase 3A: Taxiway A work - Complete

Phase 3B: Runway 27 Displaced Threshold Setup - Complete

Phase 3C: Runway 9/27 and Taxiway A5 (June 20th - August 25th) (Runway 9/27 displaced open, Runway 3/21 closed)

Phase 3D: Removal of Displaced Threshold (Anticipated August 26th - 28th) (Runway 9/27 closed, Runway 3/21 open)

Phase 3E: Sawcut Grooving (October 1st - 12th)

 For immediate information on the current airfield status, always check current NOTAM's before you fly.


Drone Panoramas:

See links below for drone panoramas taken by SEH's drone team of the project on August 9th, 2019.

Batch Plant Site: http://gis.sehinc.com/Panoramics/DULAI/BatchPlant/Aug9/

Terminal Areahttp://gis.sehinc.com/Panoramics/DULAI/Terminal/Aug9/

Project Contacts:

Duluth Airport Authority
Director of Operations     
Blaine Peterson
218.625.7767 (Office)
bpeterson@duluthairport.com

Short Elliot Hendrickson, Inc.
Project Manager
Benita Crow, PE (MN, WI)
651.919.6677 (Cell)         
bcrow@sehinc.com

Short Elliot Hendrickson, Inc.

Project Engineer
Shawn McMahon, PE ( MN, WI, IA, SD)    
651.925.7541 (Cell)
smcmahon@sehinc.com


Duluth International Airport
(218) 727-2968
daa@duluthairport.com


unsubscribe from this list    update subscription preferences