CONSTRUCTION UPDATE : CHUMPHON

Welcome to New Nordic Chumpon! Here you can find our weekly construction update from Coral Beach Chumpon Project.

Coral Beach Condominium 3

Overall construction work 65% (100%).
- Working on roof structure (100%).
- Tiling work in bathroom.
- Tiling corridor.
- Wall behind building (done).
- Aluminum fence install (done).
- Pouring the concrete for the pool (done).
- Outdoor painting.
- Indoor painting.
- Start swimming pool system.

Villa plot 29

- Painting work (done).
- Gardening around the villa.
- Start system work for swimming pool (done).
- Assemble furniture.
- Sand wash around the pool (done).
- Install gate with sliding gate with remote control.
Villa plot 31
- Start system work for swimming pool (done).
- Sand wash around the pool (done).
- Gardening around the villa.
- Assemble furniture.
- Start doing wall paper.
- Install gate with sliding gate with remote control.

Follow The Developments in Real-Time

Want to know the status of the developments while waiting for the bus? Want to know the weather in Chumphon while waiting for the coffee machine? With our New Nordic CCTV camera service, you can know what is going on at all our construction sites in real time! Follow the instructions below to upload your CCTV camera service for your project! Any questions or problems can be addressed to our IT team on itsupport@new-nordic.com.
Copyright © New Nordic Group, All rights reserved.

You are receiving this as you are an owner in the New Nordic Group or have inquired to be on our weekly news mailing list. Want to change how you receive these emails? You can update your preferences or unsubscribe from this list.