CONSTRUCTION UPDATE : PATTAYA 

Welcome to New Nordic Pattaya! Here you can find our weekly construction update from New Nordic Pattaya Project.
Construction Site: Castle 1
Overall construction 100% completed.
- Construction work 100% completed.
- Architecture work 100% completed.
- Sanitation systems work 100% completed.
- Electric work 100% completed.

 
Construction Site: Castle 2
Overall construction 98% completed.
- Bricklaying work on the underground floor 99% completed.
- Plastering underground wall 99% completed.
- Plastering work on 1st-8th floor 99% completed.
- Plastering wall work on rooftop floor 99% completed.
- Wash basin counter work 85% completed.

- Tilling work on 1st-8th floor 99% completed.
- Tilling work on rooftop floor 99% completed.
- Install skirting boards 95% completed.
- Install wood door 31% completed.
- Outdoor painting work 51% completed.
- Interior wall painting work 80% completed.
- Exterior painting work 50% completed.
- Ceiling work 96% completed.
- Installing UPCV window on 2nd-7th floor 85% completed.
- Elevator work 80% completed.

- Electric system work 1st-8th floor 99% completed.
- Water system work 97% completed.
Construction Site: Trend-7
Overall construction work 100% completed.
- Installing the furniture and decorate.
Construction Site: Boutique
Overall construction work 66% completed.
- Plastering work on 6th floor 99% completed.
- Plastering work on 7th floor 80% completed.

- Exterior plastering work 85% completed.
- Tilling bathroom wall on 3rd-5th floor 95% completed.
- Tilling bathroom wall on 6th floor 70% completed.
- Tilling on 1st floor 60% completed.
- Tilling  on 2nd-4th floor 80% completed.
- Tilling on 5th floor 70% completed.
- Tilling on 6th floor 10% completed.
- Ceiling work on 1st-4th floor 75% completed.
- Ceiling work on 5th floor 70% completed.
- Electric system work on 2nd-4th floor 92% completed.
- Water drains work on 2nd-7th floor 85% completed.

 
Construction Site: Club-4
Overall construction work 93% completed.
- Ceiling work on 1st floor 95% completed.
- Ceiling work on 2nd-7th floor 100% completed.
- Exterior painting work 98% completed.
- Painting in the room on 2nd-7th 99% completed.
- Swimming pool electrical system work 100% completed.

- Water drains work on 2nd-7th floor 100% completed.
 
Construction Site: Palace 
Overall construction work 14% completed.
- Swimming pool structure work on 1st floor 30% completed.
- Ramp floor structure work 30% completed.
- Filling the soil around buildings 40% completed.

 
Construction Site: Castle Hotel
- Electric system on 2nd floor.
- Painting ceiling work on 2nd floor.
- Wall work on 1st floor.
- Roof top work.
- Installing Air condition on 2nd floor.
Construction Site:Club-5
Overall construction work 6% completed.

- Underground pipe work 20% completed.

 
Follow The Developments in Real-Time
Want to know the status of the developments while waiting for the bus? Want to know the weather in Pattaya while waiting for the coffee machine? With our New Nordic CCTV camera service, you can know what is going on at all our construction sites in real time! Follow the instructions below to upload your CCTV camera service for your project! Any questions or problems can be addressed to our IT team on itsupport@new-nordic.com.
Copyright © New Nordic Group, All rights reserved.

You are receiving this as you are an owner in the New Nordic Group or have inquired to be on our weekly news mailing list. Want to change how you receive these emails? You can update your preferences or unsubscribe from this list.