As always, thanks for your support!
Kimberly Longey (manager)
Rebecca Coletta, Brian Hawthorne, Michal Lumsden, Sally Silberberg
P.S. You can still submit an application for the $85/month broadband service while construction crews are in town. Do so at www.whipcityfiber.com/plainfield or call (833) 923-2255 (M-F 8 a.m. to 4 p.m.). Once crews leave town there will be an additional mobilization fee to have them return, which we will pass on to you. We urge all Plainfield homeowners to apply for the service by December 31, 2019, to avoid additional charges.
P.P.S: If you signed up for a cold drop (connection to outside of house only) and now want to have full Internet service ($85/month, plus optional phone for $12.95/month), there is still time to be included in this year’s installation schedule. Please contact Whip City Fiber directly to amend your application to include broadband service (and phone, if desired).
|
|
Sequence & Approximate Timeline
for Our Town Network
Please note: We’re working as fast as we can and will accelerate as possible;
keep in mind weather delays will affect the schedule.
- FSA03: Southeast part of town (to Ashfield and Cummington borders) Network built by October 8. Customer installations begin October 21 and will take approximately 4 weeks.
- FSA01: West part of town (to Windsor and Savoy borders)
Network built by November 30. Customer installations begin December 2 and will take approximately 3 weeks.
- FSA02: South central part of town (to Cummington border)
Network built by January 11. Customer installations begin December 2 and will take approximately 2 weeks.
- FSA04: Northeast part of town (to Hawley and Ashfield border)
Network built by February 22. Customer installations begin February 24 and will take approximately 2 weeks.
|
|
|
|
|