CONSTRUCTION UPDATE : SAMUI

Welcome to New Nordic Samui! Here you can find our weekly construction update from New Nordic Samui Project.
Lamai Hotel & Resort
Building A 
Overall construction work 100% completed.
- Keep external paint work
- Install the power cord in to the Main Distribution Board.
- Install lamp wall.
- Install electrical cabinets for 3rd  floor.
- Install sanitary ware 1st and  3rd floor.
- Install aisles lamp 3rd floor.
- Install doors flame and door 4th floor.
- Painted door jamb 4th floor. 
- Install guardrail main stair 2nd and 3rd floor.
- Install guardrail fire exit stair 2nd and 3rd floor
- Install  MDB Boxes.
- Install air condition 1st -3rd floor was completed
- Install air condition 4th floor 80%
- Setting guard rail main stair 1st-4th floor.
- Setting telephone box control 1st – 4th floor.
- Tile the front elevator 1st-4th floor.
- Painted inside 1st-2nd floor.
- Fire fighting system test.
- Prepare for gardening
Building B 
Overall construction work 100% completed.
- Install ventilation fans 2nd floor.
- Install the power cord in to the Main Distribution Board.
- Install doors 1st floor.
- Install floor tiles  4th  floor.
- Install electrical cabinet for 4th floor.
- Setting up guard rail 4th floor.
- Install support water meter.
- Install glass and aluminum frame 1st and 2nd floor.
- Setting main water for tub 1st – 4th floor.
- Tile laying tub 1st – 4th floor.
- Painting skim coat 3rd -4th floor
- Install water pipes, bathtub water systems.
- Setting telephone box control 1st – 4th floor.
- Install granite on the sink counter 1st – 3rd floor.
- Install aluminum door 1st -2nd floor 95%
- Installing electrical plugs and switches 3rd floor 70%
- Install washbasin 3rd floor.
Building C (Hotel)
Overall construction work 100% completed.
- Install lamp accessories 4th floor.
- Install water meter3rd floor.
- Install the ceiling structure 4th floor.
- Install the main electrical cable set, 2nd floor
- Install up guard rail 4th floor.
- Tile laying fire exit stair 3rd and 4th floor.
- Install granite on the wash basin 4th floor.
- Check the completion of the cement under main stair 1st – 4th floor
- Painting ceiling 4th floor.
- Install guardrail fire exit stair 2nd and 3rd floor
- Setting guard rail fire exit stair 2nd-3rd floor.
- Install the lamp 4th floor.
- Setting up the electric system into the elevator.
- Painted inside 1st-2nd  floor 95% 
Building D 
Overall construction work 100% completed.
- Install SHERA wall.
- install air conditioner  2nd floor.
- Install rainwater pipes.
- Install floor tiles 2nd floor was completed.
- Plastering elevator wall.
- Setting up guard rail 4th floor was completed.
- Install electrical cabinets for 3rd and 4th floor.
- Install air conditioned 4th floor
- Install main water meter 1st and 2nd floor.
- Tile grout elevator wall 1st – 4th floor.
- Setting up ceiling under main stair 1st- 3rd  floor.
- Setting ceiling 4th floor.
- Install water pump for the building.
- Painting skim coat 4th floor.
- Masonry in front of the project to prepare the project signboard.
- Plaster wall water pump room.
- Fire fighting system test.
- Testing air conditioning systems.
Swimming pool and other
Samui Water World
Building A
- Pouring the base concrete was completed.
- Setting up the scaffold for 2nd floor.
- Pouring concrete 1st floor was completed.
- Setting groundwater storage tank frame was completed.
- Install the plumbing system 1st floor.
- Setting main pipe system 1st   floor.
- Pouring concrete elevator wall 1st floor was completed.
- Pouring concrete pole 1st floor was completed.
- Tied steel frame  2nd floor.
- Steel pole tied 2nd floor.
- Setting up floor frame 2nd floor.
- Pouring concrete 2nd floor.
- Steel frame elevator wall 2nd floor.
- Steel frame main stair 1st and 2nd floor.
- Installation of a water supply pipe system 2nd floor.
Building B
- Steel pole tie 1st floor.
- Tied steel frame elevator wall.
- Laying steel base.
- Setting main pipe system 1st   floor.
- Install the plumbing system 1st floor.
- Tied beam frame.
- Pouring concrete beam.
- Setting ground water system.
- Pouring concrete 1st floor.
- Pouring concrete elevator wall 1st floor.
- Setting up scaffold 2nd floor.
- Setting pole frame 2nd floor.
- Steel floor frame 2nd floor.
- Tie steel frame 2nd floor.
- Tie steel frame elevator wall 2nd floor.
- Installation of a water supply pipe system
Building C
- Tied steel frame elevator wall was completed.
- Pouring concrete the groundwater storage tank was completed.
- Install the plumbing system 1st floor.
- Pouring concreate post tensioned 1st floor was completed.
- Pouring concrete pole 1st floor.
- Tied steel frame 2nd floor.
- Pouring concrete 2nd floor.
- Tied steel frame elevator wall 2nd floor.
- Pouring concrete pole 2nd floor.
- Steel frame elevator wall 2nd floor.
- Steel frame main stair 1st-2nd floor.
- Installation of a water supply pipe system
- Setting scaffold for 3rd floor.
- Steel floor frame 3rd floor.
- Setting electric pipe 1st floor.
Building D 
- Cut the foundation pile.
- Pouring concrete base was completed.
- Pouring concrete pole 1st floor was completed.
- Setting up the scaffold for 2nd floor.
- Tied steel beam pool bar.
- Setting main water pipe system 1st floor.
- Tied steel frame pool bar wall.
- Install the plumbing system 1st floor.
- Tile steel pole frame 2nd floor.
- Setting up floor frame 2nd floor.
- Tied steel frame  2nd floor.
- Tie steel frame main stair 1st-2nd floor.
- Installation of a water supply pipe system
- Tie steel frame main stair 1st-2nd floor
Swimming pool and club
Follow The Developments in Real-Time
Want to know the status of the developments while waiting for the bus? Want to know the weather in Samui while waiting for the coffee machine? With our New Nordic CCTV camera service, you can know what is going on at all our construction sites in real time! Follow the instructions below to upload your CCTV camera service for your project! Any questions or problems can be addressed to our IT team on itsupport@new-nordic.com.