New Space Update
Over June & July we've had some exciting improvements in the space:
- Venue, lobby & bathrooms are painted
- Drop ceiling installed in lobby
- Venue ceiling patched
- Electrical service upgrade
- Water heater installed
- Water fountain installed
- A/C & Heat working
- Exterior ramp poured
In the coming weeks we'll have the venue ceiling painted, the concrete floor finished, and light/bathroom fixtures installed. We are getting close! We'll have more updates on the exciting exterior mural collaboration by artists Nick Nortier & Kelly Allen.
|