Heron Commences Commissioning Activities at Woodlawn Zinc-Copper Mine
- Commissioning activities are underway at the Woodlawn combined underground mine and tailings retreatment project.
- Heron and contractor commissioning teams in place.
- Hydraulic tailings retreatment preparations have commenced with infrastructure energised and water testing underway.
- Process plant commissioning has commenced with the testing of the plant control circuits.
- Commissioning of the water treatment plant is well advanced.
- First production scheduled for Qtr. 1 2019.
|
|