Heron Commences Commissioning Activities at Woodlawn Zinc-Copper Mine

  • Commissioning activities are underway at the Woodlawn combined underground mine and tailings retreatment project.
  • Heron and contractor commissioning teams in place.
  • Hydraulic tailings retreatment preparations have commenced with infrastructure energised and water testing underway.
  • Process plant commissioning has commenced with the testing of the plant control circuits.
  • Commissioning of the water treatment plant is well advanced.
  • First production scheduled for Qtr. 1 2019.
For the full announcement, please click here
For further information regarding Heron Resources, please visit www.heronresources.com.au or contact:
Heron Resources
Mr Wayne Taylor
Managing Director and CEO
Tel: +61 2 9119 8111
Email: heron@heronresources.com.au
Twitter
Copyright © 2018 Heron Resources, All rights reserved.


Want to change how you receive these emails?
You can update your preferences or unsubscribe from this list

Email Marketing Powered by Mailchimp