Works Recently Completed
  • Pedestrian crossing refurbishment substantially complete at Tesco Express near Wycombe Marsh  final lining and loop cutting to be programmed.
  • New ducting laid at Knaves Beech and Rayners Avenue.
  • New feeder pillar and communications cabinets installed at Knaves Beech and Wycombe Marsh crossings.
Traffic Management for Wycombe Marsh crossing refurbishment
Wycombe Marsh crossing refurbishment substantially complete
Knaves Beech road crossing for ducting
Station Road crossing communications cabinet installation
Footway reinstatement at Rayners Avenue for new ducting
Siding out for ducting at Knaves Beech
Upcoming Works
  • Jetting and CCTV surveys will be undertaken on existing surface water drainage and gullies along the A40 between Pinions pedestrian crossing and Citygrove junction.  Works will be undertaken in the evenings to minimise traffic disruption starting 11th March for 4 evenings (7pm to 6am).  These works will be undertaken through the use of road narrowings and temporary traffic lights at Hatters Lane roundabout.  The Citygrove signals will be temporarily switched off and temporary traffic lights used until jetting /cctv work is completed at Citygrove and then the permanent lights will be turned back on.  Advanced warning signs have been erected on site and letters delivered to affected properties.
  • Fibre cables will be laid from Knaves Beech to Rayners Avenue and at Trinity Church and adjacent to the Rye by Siemens starting 19th March 2019 for 5 days, all work in the footway so no traffic lights required.
  • CAT 5 cables to be installed between new communications cabinets and new vehicle messaging sites.
The A40 London Road corridor improvements project is a partnership project between Buckinghamshire County Council and Buckinghamshire Thames Valley Local Enterprise Partnership with funding secured from the Local Growth Fund and DfT’s National Productivity Investment Fund.

We have a dedicated mailbox for this project at hitmailbox@buckscc.gov.uk and we welcome emails and queries about the scheme, or you can email if you wish to unsubscribe from this bulletin list. You can also contact the Highways Infrastructure Team on 01296 382416.

Latest news on the A40 London Road corridor improvements project is available at www.buckscc.gov.uk/A40LondonRoad, which will be kept up to date as the project progresses.
 






This email was sent to <<Email Address>>
why did I get this?    unsubscribe from this list    update subscription preferences
Buckinghamshire Council · Walton Street Offices · Walton Street · Aylesbury, Buckinghamshire HP20 1UA · United Kingdom

Email Marketing Powered by Mailchimp