Runway 9/27 Reconstruction: Phase 3
Duluth International Airport (DLH)

Project Newsletter #2                 

 

Introduction

This is the 2nd weekly newsletter for Phase 3 of the Runway 9/27 Reconstruction project at the Duluth International Airport (DLH).  The purpose of the weekly newsletters will be to provide updates throughout the project regarding construction impacts, runway closures, temporary runway conditions, and other information as needed. Earlier versions of the newsletters will be made available upon request. In addition to the newsletters, there will be weekly tenant updates via a 15-minute GoTo meeting hosted by SEH. The first one will be held Tuesday, May 28th, at 12:30PM. The log in and call information will be provided by Blaine Peterson, Director of Operations.

 

Runway 9/27 Construction Progress

The official start to Phase 3A on Monday, May 20th began with the closure of Taxiway A, followed by paint removals, barricade and traffic control installations, pavement demolition, and continued batch plant preparation. The pavement removed from the west portion of Taxiway A was extremely thick, including nearly two feet of bituminous. The millings from the removals are being hauled to the batch plant site and reused as a base material for the plant.

Taxiway A removals:
Batch plant preparation:

 

Runway/Taxiway Operations - Phase 3A

Runway 9/27 and Runway 3/21 will be open full length for the duration of Phase 3A. Taxiway closures consist of Taxiway A east of Taxiway A5.

 

Next Week Preview:  May 26th - June 1st

Upon the completion of removals for Taxiway A, the work expected to take place will include continued grading, laying pavement base layers, drainage installations, and electrical installations.


Schedule Updates

Through the first week of construction, Phase 3A of the project has remained generally on schedule despite the rainy weather. Depending on weather or unforeseen conditions, the sub-phases are as follows:

Phase 3A: Taxiway A work (May 20th - June 18th)

Phase 3B: Runway 27 Displaced Threshold Setup (June 17th - 19th)

Phase 3C: Runway 9/27 and Taxiway A5 (June 24th - August 22nd)

Phase 3D: Removal of Displaced Threshold (August 26th - 28th)

Phase 3E: Sawcut Grooving (October 1st - 12th)

 

For immediate information on the current airfield status, always check current NOTAM's before you fly.

Project Contacts:

Duluth Airport Authority
Director of Operations     
Blaine Peterson
218.625.7767 (Office)
bpeterson@duluthairport.com

Short Elliot Hendrickson, Inc.
Project Manager
Benita Crow, PE (MN, WI)
651.919.6677 (Cell)         
bcrow@sehinc.com

Short Elliot Hendrickson, Inc.

Project Engineer
Shawn McMahon, PE ( MN, WI, IA, SD)    
651.925.7541 (Cell)
smcmahon@sehinc.com


Duluth International Airport
(218) 727-2968
daa@duluthairport.com


unsubscribe from this list    update subscription preferences