Copy

Ballard Multimodal Corridor

6/26/19 – Notification: Weekend paving work

In order to minimize impacts to businesses along the project corridor, crews will be working overnight this weekend to pour concrete on NW Market St between 28th and 24th avenues NW. This work will include paving road and driveway panels at some businesses on the north side of NW Market St. 

As a part of this work, you can expect noise from trucks, crews, and equipment on Friday and Saturday nights. We have been granted a noise variance for this work. 

The timeline for this work is as follows: 
  • Work will begin on Friday, June 28
  • Pavement demolition will start at 3 PM and should be completed by 10 PM
  • Crews will start pouring concrete at 5 PM on Friday and finish by 12 AM on Saturday, June 29
  • Work will begin again at 3 PM on Saturday 
  • Crews will finish pouring concrete by 4 AM on Sunday, June 30
Stay connected Please forward this email to others you think may be interested. 

Thanks for your patience and support while we complete this project. We’re working to minimize construction impacts as much as possible.

Ballard Multimodal Corridor
City of Seattle Department of Transportation 
 

This project will be funded by the 9-year Levy to Move Seattle, approved by voters in 2015. Learn more about the levy at www.seattle.gov/transportation/LevytoMoveSeattle

Copyright © 2019 Seattle Department of Transportation, All rights reserved.
You have received this update because of your interest in the Ballard Multimodal Corridor Project. You can opt-out of future emails regarding this project by contacting BallardMultimodal@seattle.gov with UNSUBSCRIBE in the subject line.

Our mailing address is:
Seattle Department of Transportation
PO BOX 34996
Seattle, WA 98124-4996






This email was sent to <<Email Address>>
why did I get this?    unsubscribe from this list    update subscription preferences
Seattle Department of Transportation · 700 5th Ave · Seattle, WA 98104 · USA