CONSTRUCTION UPDATE : PATTAYA 

Welcome to New Nordic Pattaya! Here you can find our weekly construction update from New Nordic Pattaya Project.
Construction Site: Castle 1
Overall construction 100% completed.
- Outdoor painting work 100% completed.
- Install door work on underground floor to rooftop 100% completed.
- Install door stop work 100% completed.
- Change the bedroom and bathroom door handle work 100% completed.
- Plastering underground floor 100% completed.
- Ceiling work on 2nd-8th floor 100% completed.
- Painting ceiling work on underground floor to rooftop 100% completed.
- Sanitation systems work 100% completed.
- Install Jacuzzi on 3rd-8th 100% completed.
- Electric work on 2nd-8th floor 100% completed.
Construction Site: Castle 2
Overall construction 90% completed.
- Bricklaying work on 1st-rooftop floor 100% completed.
- Bricklaying work on the underground floor 60% completed.
- Plastering work on 1st-8th floor 98% completed.
- Plastering wall work on rooftop floor 80% completed.
- Wash basin counter work 60% completed.

- Tilling work on 1st-8th floor 95% completed.
- Tilling work on rooftop floor 30% completed.
- Tilling fire stair work 90% completed.
- Install wall cornice 35% completed.
- Install wood door 20% completed.
- Outdoor painting work 15% completed.
- Elevator work 60% completed.
- Water system work 90% completed.
- Electric system work 90% completed.

 
Construction Site: Trend-7
Overall construction work 100% completed.
- Installing the furniture and decorate.
Construction Site: Club-3
Overall construction work 100% completed.
- Almost completed (Just wait for cleaning).

 
Construction Site: Boutique
Overall construction work 49% completed.
- Floor work on rooftop floor 15% completed.
- Plastering work on 1st-2nd floor 100% completed.
- Plastering work on 3rd floor 70% completed.

- Bricklaying on 2nd-3rd floor 100% completed.
- Bricklaying on 4th floor 98% completed.
- Bricklaying on 5th floor 60% completed.
- Bricklaying on 6th floor 100% completed.
- Tilling bathroom work on 2nd floor 95%completed.
- Ceiling work on 1st floor 50% completed.
- Ceiling work on 2nd floor 30% completed.
- Electric system work on 2nd floor 90% completed.
- Electric system work on 3rd floor 60% completed.
- Water drains work on 2nd-5th floor 85% completed.

 
Construction Site: Club-4
Overall construction work 64% completed.
- Plastering outdoor work 90% completed.
- Tilling Bathroom wall on 5th floor 100% completed.
- Tilling Bathroom wall on 6th floor 95% completed.
- Tilling Bathroom wall on 7th floor 40% completed.
- Tilling floor work on 4th floor 100% completed.
- Tilling floor 
work on 5th floor 95% completed.
- Tilling floor 
work on 6th floor 70% completed.

Ceiling work on 5th-6th floor 90% completed.
- Setting electric pipe on 5th floor 90% completed.
- Painting outdoor work 10% completed.



 
Construction Site: Palace 
- Pilling 100% completed.
- Pilling work 212 of 212 piles.
- Open basement piles 74% completed.
- Basement work 60% completed.
- Beam work 35% completed.
- Elevator wall work 12% completed.





 
Construction Site: Castle Hotel
- Plumbing work on 2nd floor.
- Tilling bathroom work on 2nd floor.
- Window outdoor work.
Construction Site:Club-5
- Planning work 100 Completed.
- Drilling piles work 57 piles of 119 piles.
Follow The Developments in Real-Time
Want to know the status of the developments while waiting for the bus? Want to know the weather in Pattaya while waiting for the coffee machine? With our New Nordic CCTV camera service, you can know what is going on at all our construction sites in real time! Follow the instructions below to upload your CCTV camera service for your project! Any questions or problems can be addressed to our IT team on itsupport@new-nordic.com.