CONSTRUCTION UPDATE : PATTAYA 

Welcome to New Nordic Pattaya! Here you can find our weekly construction update from New Nordic Pattaya Project.
Construction Site: Castle 1
Overall construction 100% completed.
- Construction work 100% completed.
- Architecture work 100% completed.
- Plastering work 100% completed.
- Ceiling work 100% completed.
- Painting work 100% completed.
- Sanitation systems work 100% completed.
- Electric work 100% completed.
- Air conditioning system work 100% completed.

 
Construction Site: Castle 2
Overall construction 91% completed.
- Bricklaying work on the underground floor 70% completed.
- Plastering work on 1st-8th floor 98% completed.
- Plastering wall work on rooftop floor 98% completed.
- Wash basin counter work 63% completed.

- Tilling work on 1st-8th floor 97% completed.
- Tilling work on rooftop floor 70% completed.
- Install wall cornice 50% completed.
- Install wood door 30% completed.
- Outdoor painting work 20% completed.
- Elevator work 72% completed.

 
Construction Site: Trend-7
Overall construction work 100% completed.
- Installing the furniture and decorate.
Construction Site: Club-3
Overall construction work 100% completed.
- Almost completed (Just wait for cleaning).

 
Construction Site: Boutique
Overall construction work 51% completed.
- Floor work on rooftop floor 100% completed.
- Plastering work on 4th floor 30% completed.

- Bricklaying on 4th floor 98% completed.
- Bricklaying on 5th floor 70% completed.
- Tilling bathroom work on 1st-2nd floor 95%completed.
- Tilling bathroom work on 3rd floor 10%completed.
- Ceiling work on 1st and 2nd floor 70% completed.
- Electric system work on 1st floor 90% completed.
- Water drains work on 2nd-5th floor 85% completed.

 
Construction Site: Club-4
Overall construction work 66% completed.
- Plastering outdoor work 98% completed.
- Install casing support work on 2nd-7th 85% completed.
- Tilling Bathroom wall on 7th floor 85% completed.
- Tilling floor work on 4th-5th floor 100% completed.
- Tilling floor work on 6th floor 90% completed.
- Tilling floor work on 7th floor 85% completed.
- Ceiling work on 5th-6th floor 90% completed.
- Ceiling work on 7th floor 80% completed.
- Setting electric pipe on 5th floor 95% completed.
- Install electrical equipment on 2nd-7th 85% completed.
- Painting outdoor work 65% completed.
- Painting in the room on 2nd-4th 60% completed.
- Painting in the room on 5th-7th 60% completed.



 
Construction Site: Palace 
Overall construction work 4% completed.
- Open basement piles 100% completed.
- Basement work 74% completed.
- Beam work 45% completed.
- Elevator wall work 12% completed.
- Bricklaying wall for the underground water tank 50 % completed.





 
Construction Site: Castle Hotel
- Tilling floor work on 1st-2nd floor.
- Tilling grout work on 2nd floor.
Construction Site:Club-5
- Planning work 100 Completed.
- Drilling piles work 110 piles of 119 piles.
Follow The Developments in Real-Time
Want to know the status of the developments while waiting for the bus? Want to know the weather in Pattaya while waiting for the coffee machine? With our New Nordic CCTV camera service, you can know what is going on at all our construction sites in real time! Follow the instructions below to upload your CCTV camera service for your project! Any questions or problems can be addressed to our IT team on itsupport@new-nordic.com.
Copyright © New Nordic Group, All rights reserved.

You are receiving this as you are an owner in the New Nordic Group or have inquired to be on our weekly news mailing list. Want to change how you receive these emails? You can update your preferences or unsubscribe from this list.