CONSTRUCTION UPDATE : SAMUI

Welcome to New Nordic Samui! Here you can find our weekly construction update from New Nordic Samui Project.
Lamai Hotel & Resort
Building A 
Overall construction work 94% completed.
- Plastering outside the building was completed.
- Setting up guard rail 1st floor was completed.
- Bathroom floor leveling 4th floor.
- Bedroom floor leveling 4th floor.
- Tile laying bathroom 4th floor.
- Tile laying 4th floor.
- Setting ceiling 3rd floor.
- Painting ceiling 3rd floor.
Building B 
Overall construction work 94% completed.
- Painting skim coat 4th floor 75%
- Plastering outside the building 90%
- Tile lying bathroom 4th  floor 50%
- Setting ceiling 3rd floor.
- Setting up elevator 95%.
- Primer paint guard rail 1st floor.
- Primer paint 1st and 2nd floor.
- Primer paint ceiling 1st and 2nd floor.
- Install sanitary ware 3rd floor.
- Plastering elevator wall 1st to 4th floor.
Building C (Hotel)
Overall construction work 94% completed.
- Setting electricity on 4th  floor was completed.
- Plaster the wall 4th floor 80%.
- Plastering outside the building 45%
- Setting ceiling frame 3rd  floor 60%
- Tile laying the balcony 2nd floor.
- Install the main electrical cable set, 2nd floor
- Tile laying 3rd floor.
- Setting ceiling frame 3rd floor.
- Primer paint ceiling 1st floor
- Setting up elevator 95%.
Building D 
Overall construction work 94% completed.
Plastering outside the building 75%
- Setting electric pipe 4th floor was completed.
- Setting up guard rail 2nd  floor.
- Setting ceiling on 2nd  floor 60%
- Setting up guard rail 2nd  floor.
- Install sanitary ware 3rd floor.
- Setting ceiling frame 3rd floor.
- Setting up elevator 95%
Samui Water World
Building A
- Cut the foundation pile
- Setting groundwater storage tank frame
- Pouring concrete underground storage tanks
- Digging pile soil
Building B
- Setting groundwater storage tank frame 1St  and 2nd
- Pouring concrete underground storage tanks 1st and 2nd
- Digging pile soil
- Steel pile tie
- Setting pile frame
- Pouring concrete pile
- Collect cement sample

 
Building C
- Setting groundwater storage tank frame 1St  and 2nd
- Tie steel on the side of the groundwater storage tank
- Clean the pile floor
- Pouring concrete storage water tank
- Water pipe system
 
Building D
- Cut the foundation pile
- Steel pile tie
- Setting pile frame
- Pouring concrete
- Pile 
steel beam
Follow The Developments in Real-Time
Want to know the status of the developments while waiting for the bus? Want to know the weather in Samui while waiting for the coffee machine? With our New Nordic CCTV camera service, you can know what is going on at all our construction sites in real time! Follow the instructions below to upload your CCTV camera service for your project! Any questions or problems can be addressed to our IT team on itsupport@new-nordic.com.
Copyright © New Nordic Group, All rights reserved.

You are receiving this as you are an owner in the New Nordic Group or have inquired to be on our weekly news mailing list. Want to change how you receive these emails? You can update your preferences or unsubscribe from this list.