CONSTRUCTION UPDATE : PATTAYA 

Welcome to New Nordic Pattaya! Here you can find our weekly construction update from New Nordic Pattaya Project.
Construction Site: Castle 1
Overall construction 100% completed.
- Construction work 100% completed.
- Architecture work 100% completed.
- Plastering work 100% completed.
- Ceiling work 100% completed.
- Painting work 100% completed.
- Sanitation systems work 100% completed.
- Electric work 100% completed.
- Air conditioning system work 100% completed.

 
Construction Site: Castle 2
Overall construction 91% completed.
- Bricklaying work on the underground floor 60% completed.
- Plastering work on 1st-8th floor 98% completed.
- Plastering wall work on rooftop floor 95% completed.
- Wash basin counter work 62% completed.

- Tilling work on 1st-8th floor 96% completed.
- Tilling work on rooftop floor 60% completed.
- Install wall cornice 45% completed.
- Install wood door 25% completed.
- Outdoor painting work 17% completed.
- Elevator work 70% completed.
- Water system work 90% completed.
- Electric system work 90% completed.

 
Construction Site: Trend-7
Overall construction work 100% completed.
- Installing the furniture and decorate.
Construction Site: Club-3
Overall construction work 100% completed.
- Almost completed (Just wait for cleaning).

 
Construction Site: Boutique
Overall construction work 50% completed.
- Floor work on rooftop floor 80% completed.
- Plastering work on 3rd floor 100% completed.

- Bricklaying on 4th floor 98% completed.
- Bricklaying on 5th floor 60% completed.
- Tilling bathroom work on 1st floor 95%completed.
- Tilling bathroom work on 2nd floor 80%completed.
- Ceiling work on 1st floor 70% completed.
- Ceiling work on 2nd floor 50% completed.
- Electric system work on 2nd floor 90% completed.
- Electric system work on 3rd floor 80% completed.
- Water drains work on 2nd-5th floor 85% completed.

 
Construction Site: Club-4
Overall construction work 65% completed.
- Plastering outdoor work 98% completed.
- Tilling Bathroom wall on 6th floor 100% completed.
- Tilling Bathroom wall on 7th floor 80% completed.
- Tilling floor work on 4th floor 100% completed.
- Tilling floor 
work on 5th floor 95% completed.
- Tilling floor 
work on 6th floor 80% completed.
- Tilling floor 
work on 7th floor 80% completed.

- Tilling floor work on 6th floor 80% completed.
- Ceiling work on 5th-6th floor 90% completed.
- Ceiling work on 7th floor 80% completed.
- Setting electric pipe on 5th floor 90% completed.
- Install electrical equipment on 2nd-7th 80% completed.
- Painting outdoor work 50% completed.



 
Construction Site: Palace 
Overall construction work 3% completed.
- Pilling work 212 of 212 piles 100% completed.
- Open basement piles 100% completed.
- Basement work 68% completed.
- Beam work 40% completed.
- Elevator wall work 12% completed.
- Pouring concrete for the ground water tank 100% completed.
- Bricklaying wall for the underground water tank 15 % completed.





 
Construction Site: Castle Hotel
- Tilling floor work on 1st-2nd floor.
- Window outdoor work.
- Tilling grout work on 2nd floor.
Construction Site:Club-5
- Planning work 100 Completed.
- Drilling piles work 98 piles of 119 piles.
Follow The Developments in Real-Time
Want to know the status of the developments while waiting for the bus? Want to know the weather in Pattaya while waiting for the coffee machine? With our New Nordic CCTV camera service, you can know what is going on at all our construction sites in real time! Follow the instructions below to upload your CCTV camera service for your project! Any questions or problems can be addressed to our IT team on itsupport@new-nordic.com.