Copy
Thanks for being part of the DLH community!

Runway 9/27 Reconstruction: Phase 3
Duluth International Airport (DLH)

Project Newsletter #10  

 

Introduction

This is the 10th weekly newsletter for Phase 3 of the Runway 9/27 Reconstruction project at the Duluth International Airport (DLH).  The purpose of the weekly newsletters will be to provide updates throughout the project regarding construction impacts, runway closures, temporary runway conditions, and other information as needed. Earlier versions of the newsletters will be made available upon request. As a result of limited participation in the weekly tenant GoTo Meeting updates, future meetings are cancelled.  However, at any time, you may request a construction update by contacting the project contacts listed in this newsletter.

 

Runway 9/27 Construction Progress

This week of construction has primarily consisted of the installation of the aggregate base layer, created by crushing the concrete that previously made up Runway 9/27. Following the placement of the material, it has been graded and compacted in an effort to achieve the required density. Also taking place this week was conduit installations for the new runway edge lights and signs, as well as the center-line lighting conduit for Taxiway A5. Due to the Duluth Airshow this weekend, construction will be on hold from today through Sunday, July 21st. Enjoy the airshow!

Crushed concrete base material in place and getting compacted:
Aerial photo showing aggregate base placement progress:

 

Runway/Taxiway Operations - Phase 3C

Phase 3C is currently underway, and Runway 9/27 is operating in the displaced condition with over 7,000' available. Runway closures consist of Runway 3/21. Taxiway closures consist of Taxiway A5, Taxiway E1, and Taxiway C north of Taxiway A.

 For immediate information on the current airfield status, always check current NOTAM's before you fly.


Next Week Preview: July 22nd  - July 28th

Next week, the aggregate base layer of crushed concrete will be fine graded and prepared for the next layer: cement treated base (CTB). The CTB will be installed beginning in the middle of the week, following final grading and compaction of the aggregate base, and will be ongoing throughout the rest of the week.


Schedule Updates

The contractor's schedule is currently tracking to be generally on schedule. Depending on weather or unforeseen conditions, the sub-phases are as follows:

Phase 3A: Taxiway A work - Complete

Phase 3B: Runway 27 Displaced Threshold Setup - Complete

Phase 3C: Runway 9/27 and Taxiway A5 (June 20th - August 22nd) (Runway 9/27 displaced open, Runway 3/21 closed)

Phase 3D: Removal of Displaced Threshold (August 26th - 28th)

Phase 3E: Sawcut Grooving (October 1st - 12th)

 For immediate information on the current airfield status, always check current NOTAM's before you fly.

Project Contacts:

Duluth Airport Authority
Director of Operations     
Blaine Peterson
218.625.7767 (Office)
bpeterson@duluthairport.com

Short Elliot Hendrickson, Inc.
Project Manager
Benita Crow, PE (MN, WI)
651.919.6677 (Cell)         
bcrow@sehinc.com

Short Elliot Hendrickson, Inc.

Project Engineer
Shawn McMahon, PE ( MN, WI, IA, SD)    
651.925.7541 (Cell)
smcmahon@sehinc.com


Duluth International Airport
(218) 727-2968
daa@duluthairport.com


unsubscribe from this list    update subscription preferences