Ten transportation projects awarded in June to the Northeast Region 


GAINESVILLE, Ga., - Ten construction projects were awarded to the Northeast Region in June that totaled just over $28 million. 

The third phase of the Cleveland Bypass in White County was awarded, representing the largest project awarded for June. 

This widening project represents an $11 million investment in White County and was awarded to CMES, Inc.
 
The project starts at the intersection of State Route 11/US 129 and ends at the intersection with State Route 75. Hulsey Road will be widened to 4-lanes with a center turn lane. This project is estimated to be complete 510 days from start date.

The widening and reconstruction on Spout Springs Road in Hall County was deferred and will be awarded at a later date. It will widen Spout Springs Rd from a two-lane roadway to a four-lane divided roadway with a 20-foot raised median and sidewalks. There will be median openings and intersections will be modified or removed accordingly. This project starts at I-985 and ends at Union Circle, spanning a total distance of 3.2 miles. Updates regarding this project will be available after the official announcement.

511 Navigator Expansion 

Additional cameras and information systems will installed at various locations along I-985 in Gwinnett and Hall Counties. This will provide HERO and CHAMP operators real-time information on traffic flow. This was awarded to Carlson Construction Services LLC for $1.5 million. The project will start in Suwanee at I-85 and I-985 and end in Gainesville at Jesse Jewell Parkway and I-985. This project has an estimated completion date of June 30, 2020.

Resurfacing Projects
  • State Route 53, in Forsyth and Dawson Counties, will be resurfaced from State Route 183 and extending south of Chestatee Height Road. C.W. Matthews Contracting Co. Inc. will be doing the work which has an estimated completion of December 15, 2020.
  • State Route 17, in Habersham and Stephens Counties, will be resurfaced by C.W. Matthews Contracting Co. Inc. between State Route 184 and State Route 365. The project has an estimated completion date of May 31, 2020.
  • State Route 115, in White County, starting at the Lumpkin County line and extending to North Bell Street. Pittman Construction Company will resurface the road with a scheduled completion date of December 15, 2020.

Rumble Strips, Signing, and Striping Upgrades 

Rumble strips, a road safety feature used to alert drivers of lane lines, will be upgraded throughout 11 counties in the region. The routes and locations below were identified by the district based on crash history.

This project was awarded to Southern States Pavement Markings, LLC for $2 million. The estimated completion date is June 30, 2020.
  • Banks: State Route 164
  • Elbert: State Routes 172, 368
  • Franklin: State Routes 8, 17, 51, 59
  • Habersham: State Routes 17, 197
  • Hart: State Routes 8, 77, 172
  • Lumpkin: State Route 9
  • Madison: State Routes 8, 98, 191, 281
  • Stephens: State Routes 17 ALT, 63, 419
  • Towns: State Route 180
  • Union: State Route 180
  • White Counties: State Routes 11, 254, 348, 356

An off-system safety project including 50 miles of highway signs, striping, and pavement markings on 25 county roads was awarded in Clarke County to Brown’s Asphalt Maintenance Inc. for $480,814. The estimated completion date for this project is June 30, 2020.
 
Barrow County also received an off-system safety project which includes nearly 50 miles of highway signs, striping, and pavement markings on 15 different roads.
This project totaled $427,971 and was awarded to Mid-States Striping Inc. June 30, 2020 is the estimated completion date for this project.
 
Habersham County will also receive signing and striping upgrades on various county roads. This project was awarded to Roadscape North Florida and totals $155,527.
This project spans 42 miles and includes highway signs, striping, and pavement marking on 15 county roads in Habersham. June 30, 2020 is the estimated completion date.
 
Additional details and lane closures related to these project will be communicated as construction begins.
 
Follow Us Follow Us
Like Us Like Us
Visit Us Visit Us
See Us See Us
Watch Us Watch Us
The information you provide to the Georgia Department of Transportation will be used solely by GDOT. The Department does not sell or offer a subscriber's personal information to third parties for marketing purposes. To no longer receive this e-news letter, please select "unsubscribe from this list" below.
The information you provide to the Georgia Department of Transportation will be used solely by GDOT. The Department does not sell or offer a subscriber's personal information to third parties for marketing purposes. To no longer receive this e-news letter, please select "unsubscribe from this list" below.
For questions, contact Katie Strickland.
Copyright © 2018 Georgia Department of Transportation, All rights reserved.

Our mailing address is:
Georgia Department of Transportation
Office of Communications
600 West Peachtree Street N.W.
Atlanta, GA 30308

Want to change how you receive these emails?
You can update your preferences or unsubscribe from this list