CONSTRUCTION UPDATE : PATTAYA 

Welcome to New Nordic Pattaya! Here you can find our weekly construction update from New Nordic Pattaya Project.
Construction Site: Castle 1
Overall construction 100% completed.
- Construction work 100% completed.
- Architecture work 100% completed.
- Sanitation systems work 100% completed.
- Electric work 100% completed.

 
Construction Site: Castle 2
Overall construction 95% completed.
- Bricklaying work on the underground floor 95% completed.
- Plastering work on 1st-8th floor 98% completed.
- Plastering wall work on rooftop floor 98% completed.
- Plastering underground wall 80% completed.
- Wash basin counter work 85% completed.

- Tilling work on 1st-8th floor 98% completed.
- Tilling work on rooftop floor 98% completed.
- Tilling main stair work 99% completed.
- Install skirting boards 80% completed.
- Install wood door 30% completed.
- Outdoor painting work 35% completed.
- Wall painting 40% completed.
- Ceiling work 65% completed.
- Sky roof work 100% completed.
- Elevator work 75% completed.

- Electric system work 2nd-7th floor 98% completed.
- Water system work 96% completed.
Construction Site: Trend-7
Overall construction work 100% completed.
- Installing the furniture and decorate.
Construction Site: Club-3
Overall construction work 100% completed.
- Almost completed (Just wait for cleaning).



( Open on August 2019)
Construction Site: Boutique
Overall construction work 60% completed.
- Plastering work on 4th floor 95% completed.

- Bricklaying on 6th floor 60% completed.
- Bricklaying on 7th floor 40% completed.
- Tilling bathroom work on 4th floor 80%completed.
- Ceiling work on 1st-3rd floor 75% completed.
- Ceiling work on 4th floor 60% completed.
- Electric system work on 2nd-3rd floor 92% completed.
- Electric system work on 4th floor 60% completed.
- Water drains work on 2nd-7th floor 85% completed.

 
Construction Site: Club-4
Overall construction work 83% completed.
- Plastering on 1st floor 40% completed.
- Tilling Bathroom wall on 2nd-7th floor 99% completed.
- Tilling the walk way on 2nd-7th floor 99% completed.
- Tilling in room on 2nd-7th floor 99% completed.
- Tilling balcony on 2nd-7th floor 99% completed.
- Tilling balcony on 2nd-4th floor 99% completed.
- Tilling main stair on 1st-7th floor 99% completed.
- Tilling fire stair on 1st-7th floor 99% completed.
- Ceiling work on 2nd-7th floor 99% completed.
- Painting outdoor work 90% completed.
- Painting in the room on 5th-7th 80% completed.
- Installing UPVC window work on 2nd-7th floor 98% completed.
- Installing UPVC door work on 2nd-7th floor 98% completed.
- Water system work 90% completed.
- Setting electric pipe on 2nd-7th floor 99% completed.
- Install electrical equipment on 2nd-7th 99% completed.



 
Construction Site: Palace 
Overall construction work 9% completed.
- Beam work 95% completed.
Retaining wall 40% completed.
- Underground floor work 70% completed.
Construction Site: Castle Hotel
- Installing the roof top.
- Ceiling work.
Construction Site:Club-5
Open the foundation piles 52% completed.
- Cutting foundation piles 52% completed.
- Adjust the soil 52% completed.
Pouring concrete base.
 
Follow The Developments in Real-Time
Want to know the status of the developments while waiting for the bus? Want to know the weather in Pattaya while waiting for the coffee machine? With our New Nordic CCTV camera service, you can know what is going on at all our construction sites in real time! Follow the instructions below to upload your CCTV camera service for your project! Any questions or problems can be addressed to our IT team on itsupport@new-nordic.com.