Peterson/Ridge Metra Project Update
May 13, 2022
Dear Neighbor,
Here is your weekly update of the scheduled tasks for the Metra Peterson/Ridge Project this past week, and the scheduled tasks we intend to begin the upcoming week.
Monday, May 9th thru Friday, May 13th Work Performed
- Frame Warming House Wall – West of UPRR Tracks - JBCC
- Excavate Between Sheeting to Remove Retaining Wall – West of UPRR Tracks – JBCC
- Demo Retaining Wall – West of UPRR Tracks - JBCC
- Install Rebar For Warming House Wall – West of UPRR Tracks – All J Steel
- Install Clips and Studs on Sheeting – East Of UPRR Tracks - Michels
- Location of Work
- East and West Track Side Between N Ridge and West Peterson Ave.
- Southeast Track Side Along N Ravenswood and South of Peterson Ave
- Public Disruption
- Sidewalk Closure = Full Closure – 6000 N Ravenswood – 6100 N Ravenswood - CLOSED
- Road Closures = Northbound 6000 N Ravenswood – 6100 N Ravenswood - CLOSED
Monday, May 16th thru Friday, May 20th, Work Performed
- Frame Warming House Wall – West of UPRR Tracks - JBCC
- Excavate Between Sheeting to Remove Retaining Wall – West of UPRR Tracks – JBCC
- Demo Retaining Wall – West of UPRR Tracks - JBCC
- Install Rebar For Warming House Wall – West of UPRR Tracks – All J Steel
- Install Clips on Back Wall Ramp 2 & 3 – East of UPRR Tracks – Michels
- Pour Warming House Wall – East of UPRR Tracks - JBCC
- Location of Work
- East and West Track Side Between N Ridge and West Peterson Ave.
- Southeast Track Side Along N Ravenswood and South of Peterson Ave
- Public Disruption
- Sidewalk Closure = Full Closure – 6000 N Ravenswood – 6100 N Ravenswood - CLOSED
- Road Closures = Northbound 6000 N Ravenswood – 6100 N Ravenswood - CLOSED
If you have additional questions, please email our office at info@40thward.org. Know someone who would like to join our mailing list? Sign up at Metra Ridge/Peterson Station Project.
Yours in Service,
Alderperson Andre Vasquez, 40th Ward
|
|
|
|
|