Educational Facilities:
Alexandria City High School: King Street Campus
- Parking garage repairs on-going, currently working on phase 8 of 10.
- Additional fencing work on-going and is 90% complete.
- Perimeter fence adjacent to stadium out for bid.
Charles Barrett Elementary School
- HVAC renovation project approved, contract executed, submittals commenced.
- Phase II of asbestos flooring remediation and floor leveling in kindergarten commenced (remaining classrooms).
Cora Kelly for Math, Science and Technology
- Playground poured-in place surfacing repairs completed, equipment repairs completed.
- Office carpeting delayed; installation projected for fall.
- Library lighting project scoped, pricing underway.
Ferdinand T. Day Elementary School
- Interior renovation being scoped.
- Parking garage repairs on-going, currently working on phase 8 of 10.
Francis C. Hammond Middle School
- Asbestos flooring remediation commenced.
- Building envelope / water intrusion - skybridge water test scheduled.
- HVAC renovation work is ongoing.
- Stormwater weeps at planter box scheduled for summer.
- Water bottle filling station replacements complete.
- Courtyard Drainage and stormwater management redesign is ongoing.
George Washington Middle School
- HVAC renovation work is ongoing in phases, fan coil unit installation commenced.
- Gymnasium painting is scheduled.
- Field Renovation - design work is ongoing.
- Next phase of asbestos flooring remediation scoped, priced, scheduled.
- Gymnasium Lobby Restrooms renovation commenced.
- Gymnasium Lobby Renovation commenced.
- Gymnasium tile repair work scheduled over summer.
John Adams Elementary School
- Stormwater management improvements being scoped and scheduled.
- Library renovation commenced.
- Hardscape improvements being priced.
James Polk Elementary School
- Kindergarten cabinets, countertops, sinks scheduled for summer.
- Next phase of asbestos flooring remediation scoped, priced, being scheduled for summer.
- Stormwater management and erosion engineering study to be performed over summer.
- Restroom countertops scheduled for summer.
Lyles Crouch Traditional Academy
- Outdoor learning, playground, and fields stormwater retention calculations being engineered.
- Parking lot repairs being scheduled for summer work.
- New display cases created on first and second floor hallways.
- Library painting being scoped.
- Kitchen renovation schematic design complete.
Mount Vernon Community School
- Phase III emergency asbestos remediation for ceiling tile and floor commenced.
- Kitchen/cafeteria renovation punch list ongoing; walk-in cooler/freezer installed.
- Library renovation is ongoing, construction work schedule.
- Courtyard stormwater management improvement design permitted.
- New chiller ordered and awaiting summer delivery.
Naomi L. Brooks Elementary School
- Security safety vestibule design commenced.
- Media Center renovation design commenced.
- Interior painting scheduled for summer.
- Asbestos remediation and carpet removal commenced.
- Window replacement components being phased.
Samuel W. Tucker Elementary School
- Carpet replacement scheduled for summer.
- Playground resurfacing scheduled for summer.
- Interior painting scheduled for summer.
- Column tuck-pointing scheduled for summer.
William Ramsay Elementary School
- Stormwater management and erosion engineering study commenced.
- Kitchen renovation design ongoing, starting construction documents phase.
- Building envelope engineering study commenced.
- LVT flooring tile repairs schedule was delayed due to additional summer school usage.
|