Welcome to the 12th issue of PGCPS Blueprint Schools News and Updates!
 For more information about the program, please visit www.pgcpsblueprintschools.com.
Colin L. Powell K-8 Academy
Topping Out Ceremony
A topping-out ceremony was held last month at the Colin L. Powell K-8 Academy (formerly known as the Southern Area K-8 Academy) site to celebrate the last steel beam being placed atop the new building structure. The ceremony, hosted by Gilbane Building Company, was attended by Dr. Monica Goldson (PGCPS CEO), County Executive staff, Brandey McDonald (Fengate Project Director), and Jason Washington (Blueprint Schools Program Director). Attendees provided brief remarks, went on a tour of the construction site, and signed the steel beam. This ceremony marks significant milestones reached within the Blueprint Schools Program as all six school sites are on schedule for summer 2023 delivery.
Construction Updates

ADELPHI MIDDLE SCHOOL

Project Executive: Christian Broyles

Past Month’s Accomplishments:
  • MEPF hangers installation and interior wall layout at building sectors 2A and 2B completed.
  • Installation and pouring of concrete stair tread infills at stair 2 completed.
  • Spraying of fireproofing and ceiling hat channel installation at building sector 1B completed.
  • Exterior wall panel installation at building sector 2G completed.
  • Framing out of interior walls on level 1 of building sector 1B completed.
  • Ceiling metal lath installation on level 2 of building sector 1B completed.
  • Underground site storm water infrastructure at parking lot area completed.
  • Interior CMU block walls in the gym completed.
  • MEP above ceiling rough-in and exterior brick installation at building sector 1A completed.
  • Site storm water utilities installation at soccer field completed.
  • Installation of ceiling metal lath, MEPF hangers, and interior wall layout on level 2 of building sector 1B in progress.
  • Installation of site underground sanitary piping in progress.
  • Installation of exterior brick, building foundation wall waterproofing, and backfill at building sector 1B in progress.
  • Spraying of fireproofing ceiling lath at building sector 1A in progress.
  • MEPF rough-in at building sector 1B, east commons, and gym in progress.
  • Installation of TPO roofing at east commons in progress.
30-Day Look Ahead:
  • Interior stud wall framing on level 2 of building sector 1A is ongoing.
  • MEP ceiling rough-in at building sector 1B and level 2 of building sector 1A is ongoing.
  • MEPF hangers installation on level 2 of building sector 1B to be completed.
  • Exterior brick around the perimeter of the building to be completed.
  • Installation of exterior wall panels in building sectors 1A and 1B to continue.
  • Installation of the site underground utilities is ongoing.
  • Installation of TPO roofing at the east and west commons to be completed.
DREW-FREEMAN MIDDLE SCHOOL
Project Executive: Christian Broyles
 
Past Month’s Accomplishments:
  • Installation of roof panels in building sectors 1B and 2K completed.
  • Installation of interior CMU block walls in building sector 2K completed.
  • Installation of interior wall framing in building sector 1A completed.
  • Secondary exterior steel erection in building sectors 1A and 1B completed.
  • Installation of site underground storm/sanitary lines on west side of the building completed.
  • Spraying of fireproofing in building sectors 1B and 2G in progress.
  • Installation of interior CMU block walls in building sector 2G in progress.
  • Installation of interior wall framing in building sector 1B in progress.
  • Installation of MEPF in building sectors 1A and 1B in progress.
  • Installation of exterior brick and drywall top out in building sector 1A in progress.
  • Installation of site underground water utility piping to the building in progress.
30-Day Look Ahead:
  • Installation of exterior brick in building sectors 1B and 2K is ongoing.
  • Installation of MEPF in first floor of building sectors 1A and 1B is ongoing.
  • Spraying of fireproofing in building sectors 2G and 2K is ongoing.
  • Installation of MEPF rough-ins and fire protection on level 2 of building sector 1A is ongoing.
HYATTSVILLE MIDDLE SCHOOL
Project Executive: Arland Knipe

Past Month’s Accomplishments:
  • Elevator shaft top out at building sector 1B completed.
  • HVAC ductwork risers in building sector 1A tower completed
  • Installation and pouring of concrete stair tread infills at the stair 3 egress in building sector 1A completed.
  • Spraying of fireproofing on the 3rd floor of building sector 1A completed.
  • Exterior metal wall panel installation at building sectors 1A and 2G completed.
  • Roof parapet framing and blocking at building sector 1A completed.
  • Ceiling hat channel installation at building sector 2K completed.
  • Secondary steel installation at building sectors 1B and 2G in progress.
  • Building perimeter knee wall construction and installation of exterior metal wall panels at building sector 2G in progress.
  • Sprinkler installation and electrical overhead rough-in on 1st floor of building sector 1A in progress.
  • Interior wall framing and one-siding drywall on floors 1 and 2 of building sector 1A  in progress.
  • Spraying of fireproofing on floor 2 of building sector 1B in progress.
  • Installation of MEP ceiling hangers and interior stud wall framing floor 1 of building sector 1B in progress.
  • Stair 2 installation at building sector 1A tower in progress.
  • Site underground storm water and water line utilities at south side of building in progress.
  • Interior CMU block wall bracing installation at building sector 2G in progress.
  • Roof parapet framing and blocking in progress.
30-Day Look Ahead:
  • Exterior metal wall panel installation at building sector 2G to begin.
  • MEP overhead rough-in, testing, and insulation is ongoing.
  • Sprinkler installation at Sector 1A tower is ongoing.
  • Overhead HVAC ductwork installation at building sectors 1A and 1B towers is ongoing.
  • Spraying of fireproofing at building sector 1B to continue.
  • TPO roofing installation at building sector 1A is ongoing.
  • Secondary steel installation at building sector 1B tower is ongoing.
KENMOOR MIDDLE SCHOOL
Project Executive: Christian Broyles

Past Month’s Accomplishments:
  • Backfill at the perimeter of the building completed.
  • Interior stud wall framing at level 1 of sector 1A and sector 2K completed.
  • Spraying of fireproofing in sectors 2K and 2G completed.
  • Roof panel installation in sector 2G completed.
  • Overhead and in-wall mechanical and plumbing rough-in on level 1 of sector 1B completed.
  • Site underground sanitary utility piping completed.
  • Installation of exterior wall panels at sectors 1A, 2K and 2G in progress.
  • Installation of TPO roofing at sectors 1A, 1B, 2K and 2G in progress.
  • Overhead and in-wall MEP rough-in on level 1 of sector 1A in progress.
  • Installation of electrical raceways ceiling rough-in in sector 1A and level 1 of sector 1B in progress.
  • Installation of overhead MEP rough-in in Sector 2K in progress.
  • Electrical rooms rough-in and installation of windows in progress.
30-Day Look Ahead:
  • Spraying of fireproofing ceiling lath on level 2 of sector 1A and sector 1B to be completed.
  • Interior stud wall framing at sector 1B level 2 to begin.
  • MEP ceiling and wall rough-in in building sector 2K and level 2 of 1B is ongoing.
  • Installation of exterior wall panels in building sectors 1A and 2G is ongoing.
  • Installation of site underground water and storm utilities to begin.
COLIN L. POWELL K-8 ACADEMY
Project Executive: Arland Knipe

Past Month’s Accomplishments:
  • All concrete slab on grade completed.
  • Steel erection at building sequences 3A and 3B (4-story tower) completed.
  • Metal decking installation at levels 2 and 3 of the 4-story tower completed.
  • Secondary steel erection at building sequence 2 completed.
  • Roofing at building sequence 1 (kitchen and dining areas) completed.
  • Storm utility work at the south parking area completed.
  • Spraying of fireproofing, MEP hangers and ductwork installation, and exterior brick installation in building sequence 1 in progress.
  • Metal decking installation on level 4 of the 4-story Tower in progress.
  • Interior CMU block wall construction at the main gym and stage in progress.
  • Parapet exterior framing and sheathing at building sequence 2 in progress.
30-Day Look Ahead:
  • Construction of retaining wall to begin.
  • Installation of TPO roofing at building sequence 2 to begin. 
  • Concrete slab on metal deck pours at level 2 of the 4-story tower to begin.
  • Steel erection at the 3-story tower to begin.
  • Installation of HVAC ductwork and overhead plumbing in building sequence 1 is ongoing.
WALKER MILL MIDDLE SCHOOL
Project Executive: Christian Broyles

Past Month’s Accomplishments:
  • Roof panel installation at building sectors 1A and 2G completed.
  • Interior stud wall framing at sector 1B completed.
  • Installation of exterior brick at sector 1B and 2K completed.
  • Wall layout at sector 1A completed.
  • Installation of interior MEP overhead rough in sector 1B in progress.
  • Spraying of fireproofing at building sector 1A in progress.
  • Installation of interior CMU block walls at building sectors 2K and 2G in progress.
  • Installation of exterior wall panels at sector 2K in progress.
  • Installation of CMU support steel at sector 2G in progress.
30-Day Look Ahead:
  • Installation of metal ceiling lath at building sector 1B to begin.
  • Interior wall framing, MEP overhead rough-in, and TPO roof installation at sector 1A to begin.
  • Exterior brick ledge at sector 1A to be completed.
  • Installation of exterior wall panels at sector 1B to be completed.
  • Installation of underground site utilities throughout the project site to begin.
  • Installation of underground water line division valve on Karen Blvd to be completed.
 

*Please note: Construction timeframes shown above are subject to change.

For questions and inquiries on construction in your neighborhood,
please call (301) 317-6199 or email
blueprintschoolsinfo@gilbaneco.com 
PGCECP Donates $20,000 to the
Prince George's Community College Foundation

 
Prince George’s County Education and Community Partners (PGCECP) presented a scholarship to the Prince George's Community College Foundation for students studying in science, technology, engineering or math (STEM) fields.
 
The scholarship will directly support students in PGCC's STEM Collegian Center. The Center's goal is to provide a supportive and rewarding environment to encourage, improve, and commend student success in science, technology, engineering, mathematics, and related fields. This is accomplished through academics, faculty mentoring, internships, student projects, field trips, conferences, and peer interaction.
 
PGCECP is a partnership comprising Gilbane Building Company, Corenic Construction and Warren Builds. The team is dedicated and proud to support the next generation of infrastructure creators.
Know someone else who would like to receive Blueprint Schools
Program News & Updates
? Tell them to sign up
HERE

For more information about the program, please visit www.pgcpsblueprintschools.com






This email was sent to <<Email Address>>
why did I get this?    unsubscribe from this list    update subscription preferences
Brailsford & Dunlavey · 1140 Connecticut Ave NW Ste 400 · Washington, DC 20036-4014 · USA

Email Marketing Powered by Mailchimp