Educational Facilities:
Alexandria City High School: King Street Campus
-
Parking garage repairs on-going, currently working on phase 9 of 10.
-
Additional fencing work complete with some additional scope being added.
-
Perimeter fence ITB contractor site visit held.
Charles Barrett Elementary School
-
HVAC renovation project ongoing.
-
Phase II of asbestos flooring remediation in kindergarten is complete.
-
Kindergarten LVT installation commenced.
Cora Kelly for Math, Science and Technology
-
Office carpeting delayed; installation projected for fall.
-
Library lighting project scoped, pricing underway.
Ferdinand T. Day Elementary School
-
Interior renovation being scoped.
-
Parking garage repairs on-going, currently working on phase 9 of 10.
Francis C. Hammond Middle School
-
Asbestos flooring remediation complete.
-
Building envelope / water intrusion - skybridge water test complete.
-
HVAC renovation work is ongoing.
-
Courtyard Drainage and stormwater management redesign is ongoing.
-
Gymnasium Lobby Renovation ongoing.
George Washington Middle School
-
HVAC renovation work is ongoing in phases, fan coil unit and RTU installation ongoing.
-
Gymnasium painting resumed.
-
Field Renovation - design work is ongoing; community meeting being planned.
-
Asbestos flooring remediation complete.
-
Gymnasium Lobby Restrooms renovation ongoing.
-
Gymnasium Lobby Renovation ongoing.
-
Gymnasium tile repair work scheduled.
John Adams Elementary School
-
Stormwater management improvements being scoped and scheduled.
-
Library renovation ongoing.
-
Hardscape improvements being scheduled.
James Polk Elementary School
-
Kindergarten cabinets, countertops, sinks ongoing.
-
Asbestos flooring remediation complete.
-
LVT and carpet installation ongoing.
-
Stormwater management and erosion engineering study ongoing.
-
Restroom countertops ongoing.
Lyles Crouch Traditional Academy
-
Outdoor learning, playground, and fields stormwater retention calculations ongoing.
-
Parking lot repairs being scheduled for summer work.
-
New display cases complete.
-
Library painting being scoped.
-
Kitchen renovation design development phase ongoing.
Mount Vernon Community School
-
Phase III emergency asbestos remediation for ceiling and floor tile complete.
-
Kitchen/cafeteria renovation punch list ongoing; dock ramp scheduled.
-
Library renovation construction is ongoing.
-
Courtyard stormwater management improvement design permitted.
-
New chiller ordered and awaiting fall delivery.
-
Front parapet wall and concrete removal planned.
Naomi L. Brooks Elementary School
-
Security safety vestibule design ongoing.
-
Media Center renovation design commenced.
-
Interior painting ongoing.
-
Asbestos remediation / carpet removal complete, LVT installation commenced.
-
Window replacement project on hold.
Samuel W. Tucker Elementary School
-
Carpet replacement in break-out areas now scheduled for fall.
-
Playground surfacing scheduled for summer.
-
Interior painting of the main hallway complete.
-
Column tuck-pointing and kindergarten window repairs complete.
William Ramsay Elementary School
-
LVT flooring tile repairs schedule was delayed due to additional summer school usage.
-
Building envelope engineering study ongoing.
-
Kitchen renovation design ongoing, construction documents in process.
-
Stormwater management and erosion engineering study ongoing.
|