Construction Paused to Address Conflicts with Existing Utilities
Work on the project has been temporarily halted due to conflicts with existing gas/telecommunication utilities. These utilities in conflict need to be relocated at multiple locations before our contractor can install the new water and wastewater lines.
The project team is currently working on these concerns and planning for the remaining outstanding effort. It is expected to take about 6 to 8 weeks before the crew will mobilize again to complete the rest of the work. Once we get closer to getting back onsite, we will provide a newsletter update on where the crew will start their work. Please note that the contractor will need to jump from one location to another to meet the work sequence.
If you have questions about this project, please feel free to contact a member of the project team below. We look forward to completing the necessary utility improvements in your neighborhood.