Weekly Flood Update
Friday, July 30, 2021
|
|
Please see below Texas Township's weekly update regarding the flooding crisis and other activities and events in the Township.
Lake Level Comparisons
Date of Measure: Thursday, July 29
Eagle Lake
- Down 36.24 inches from the highest point.
- Target Level Comparison: Exceeding target by 12.96"
- Normal Lake Comparison: Exceeding level by 18.24"
Crooked Lake
- Down 38.16 inches from the highest point.
- Target Level Comparison: Exceeding target by 3.36"
- Normal Lake Comparison: Exceeding level by 3.36"
Pine Island Lake
- Down 27.00 inches from the highest point.
|
News & Events
Office Hours
The office is open for service.
Mon - Thu | 8:00am-4:30pm
Fri | 8:00am-11:30am
Upcoming Meetings
|
|
Updates
- We were awarded a FEMA HMGP in the amount of $772,275 with a Township match of $257,425, totaling $1,029,700. At the time the grant was submitted the long term project was not designed but the estimated project cost was $1.3 million, this grant award was based off of that estimate. We know believe the project cost will be closer to $1.65 million, now that more of the project design has been completed. We will have an opportunity to request additional funds from FEMA to assist with the added costs.
- The Township Board formally accepted the grant at their July 26, 2021 Board Meeting.
- The acceptance of the FEMA Grant will not affect the timeline as the Drain Office has authorized Prein & Newhof to continue designing the project.
- The Task Force met on July 22, 2021. The summary can be found here.
|
|
Next Flood Task Force Meeting
Thursday, August 26, 2021 at 10:30am via Zoom
|
|
|
|
|
|
|