Construction has begun! All six schools are officially in the hands of the design-build team, led by Gilbane Building Company. Below is a construction update at-a-glance:*
Construction Leadership
Michael Ricketts, Senior Project Executive (P3 Program)
Brian Malanchuk, Senior Project Executive (Construction)
Jumanne Smith, Construction Executive
ADELPHI AREA MIDDLE SCHOOL
Project Executive: Christian Broyles
Past Month’s Accomplishments:
- Site perimeter surveying and fencing completed
- Installation of erosion and sediment control measures at site perimeter and construction entrances underway
- Clearing of trees and school demolition underway
30-Day Look Ahead:
- Completion of site perimeter erosion and sediment control
- Installation of electricity and internet at jobsite trailer in progress
- Installation of sediment ponds to commence
- School demolition to continue
DREW-FREEMAN MIDDLE SCHOOL
Project Executive: Christian Broyles
Past Month’s Accomplishments:
- Site perimeter surveying and fencing completed
- Interior building abatement and demolition in progress
30-Day Look Ahead:
- Erosion and sediment control at site perimeter to be installed
- Rough grading and school demolition to begin
- Onsite installation of the haul road and crane pad to commence
- Construction of concrete building foundations to begin
HYATTSVILLE MIDDLE SCHOOL
Project Executive: Arland Knipe
Past Month’s Accomplishments:
- Site perimeter surveying and fencing completed
- Installation of erosion and sediment control measures at the site perimeter and construction entrances underway
- Interior abatement underway
30-Day Look Ahead:
- Completion of site perimeter erosion and sediment control measures
- School demolition to begin
- Tree and grass removal to begin
- Grading of the site to commence
- Construction of concrete building foundations to begin
KENMOOR MIDDLE SCHOOL
Project Executive: Christian Broyles
Past Month’s Accomplishments:
- Site perimeter surveying and fencing completed
- Installation of temporary electricity to jobsite
- Installation of erosion and sediment control measures at site perimeter and construction entrances underway
30-Day Look Ahead:
- Completion of site perimeter erosion and sediment control measures
- Tree and grass removal to commence
- Rough grading of the site to begin
- Grading of the building pad to begin
- Construction of concrete building foundations to begin
SOUTHERN AREA K-8 ACACEMY
Project Executive: Arland Knipe
Past Month’s Accomplishments:
- Site perimeter surveying and fencing completed
- Site perimeter tree removal and erosion and sediment control measures in progress
30-Day Look Ahead:
- Completion of site perimeter erosion and sediment control measures
- Installation of the jobsite trailer and tree protection fencing
- Sediment trap excavation to commence
- Site clearing to begin
WALKER MILL MIDDLE SCHOOL
Project Executive: Christian Broyles
Past Month’s Accomplishments:
- Site perimeter surveying and fencing completed
- Installation of temporary electricity to the jobsite completed
- Perimeter erosion and sediment control measures in progress
30-Day Look Ahead:
- Completion of site perimeter erosion and sediment control measures
- Sediment trap installation to begin
- Rough grading of the site to begin
- Surcharge of the site, hauling dirt into the site, to commence
*Please note: Construction timeframes shown above are subject to change.
|