Scholls Ferry Road Area Pipeline Project (PLM_5.3)
This segment of the pipeline includes approximately 20,000 linear feet of 66-inch diameter, welded steel pipe. The pipeline alignment begins just north of the intersection of SW Tile Flat and SW Grabhorn Roads, to connect to the recently installed PLM_5.2 pipeline to the south. The pipeline alignment travels north following Grabhorn Road to the future water storage tanks at the intersection of SW Grabhorn and SW Stonecreek Drive. The pipeline alignment then travels west on private property until it reaches the existing Bonneville Power Administration (BPA) corridor where it will travel north following the BPA corridor to SW Farmington Road. North of Farmington Road, the pipeline alignment is within a potential future Cornelius Pass Road corridor through private property where it will connect to the South Hillsboro Pipeline Project (PLW_1.0), which is currently under construction and is anticipated to be complete in 2022.
|
|