Over the next month, the first phase of the Sustainable Infrastructure Program will wrap up for this year. This is a four-year program and wrapping up our first year of construction is a major step toward achieving a carbon-neutral campus.  

This week, activity will continue in the Wilder Bowl, as we work on a segment of distribution pipes installed this summer. Please be mindful of wayfinding and construction signage in this area, and we expect sidewalks to be opened up by early next week.

As for the remaining 2021 work, the project team is completing campus building conversions, restoring campus hardscapes and landscaping, flushing and testing the new hot water and chilled water piping systems, and preparing the hot water system for the upcoming heating season.

Areas of outdoor work will be restored as this work concludes, but we will continue to update wayfinding maps as conditions shift. Updates maps can be found on the  Activity Page.

Over the next four to six weeks, the following activities will be occurring as the Program team finishes up this year’s work:
  • Remaining trenches will be backfilled, and the disrupted areas reseeded for grass or other plantings
  • Sidewalks will be restored and available for pedestrian traffic
  • Street paving will be completed on Professor Street and Elm Street
  • Tree planting will start
  • Building mechanical and electrical systems will be fine-tuned as outdoor air temperatures change
  • Mobile boilers will remain on the west side of Lord Saunders and north side of Harvey Kade Price to support our transition from steam to hot water. The Lord Saunders boiler will remain for the winter. The Harvey Kade Price boiler should be removed in late November.
  • Pipe, materials, and equipment will be removed from the campus
  • Work will continue in the central services building to prepare for next year’s campus heating and cooling needs
  • The east parking lot at the central services building will be restored and repaved
Parking (View Parking Map)
To accommodate staging and contractor parking for SIP and for Mudd renovation, changes to and alternative accommodations for faculty and staff are expected for the following lots:
  • The Service Building East lot is unavailable until late-October.
  • Contractors will utilize marked parking spots in the Gray Gables parking lot through the duration of the project. There will be approximately 25 parking spaces available for staff and they will be marked accordingly.
Also, please note all impacted faculty and staff are not limited to the designated alternative accommodations outlined here should another lot on campus better suit their schedule and campus pathway. 

Other Work on Campus
Beyond the Sustainable Infrastructure Program, some other work activities on campus will have an impact on pedestrian and bike traffic. The Center for Engaged Liberal Arts (CELA) project continues in the Mudd building. This project involves a renovation of Mudd A-level into new student counseling, engagement and activity space. It involves a complete rebuild of the former Center for Information Technology spaces and lower courtyard enhancements to all direct access to CELA from the A-level courtyard. This work includes installation of a new concrete ADA ramp for the lower courtyard. Concrete is currently being removed from the plaza, and this concrete work will continue through the end of October. In support of this work, the sidewalk heading in the southwest direction from Mudd Library will be designated for equipment through the end of October, and wayfinding signs will identify pathways for pedestrians and bikers to follow.

For questions regarding the Mudd/CELA project, please contact Brad Burrer at bburrer@oberlin.edu (440-935-0909).
 
You are receiving this email because you are a stakeholder of Oberlin College's Sustainable Infrastructure Program. You can update your preferences or unsubscribe from this list.

 






This email was sent to <<Email Address>>
why did I get this?    unsubscribe from this list    update subscription preferences
Ever-Green Energy · 305 Saint Peter St · Saint Paul, MN 55102-1607 · USA

Email Marketing Powered by Mailchimp