Copy
Greetings | تحية طيبة  | ሰላም I Nagga qaabaadha I Saludos | Salaamu caleykum I Pagbati I Chào bạn |
POSTPONED: SW Oregon St intersection closure 
Roadway paving continues with delays due to wet weather

Construction started June 2020 and is expected to continue through 2022.

Please share this email with others who might be interested in receiving project information and construction updates, and feel free to get in touch with us if you have any questions.

You may sign up for email updates using this form.
Translations now available

Para leer esta alerta en Español, visite nuestro sitio web del proyecto

Para basahin ang update na ito sa Tagalog, bisitahin ang aming website para sa proyekto

Để đọc email cập nhật này bằng Tiếng Việt, hãy truy cập trang web dự án của chúng tôi
Maxaad filan kartaa waqtiga dhismuhu socodo
 
REMINDER: Businesses along the corridor are open during this work. Please follow posted detour signs as you visit these businesses.
What to expect the week of October 12
We are currently working in all three zones at the same time, from north to south on Delridge Way SW. As our work zones shift you will see No Parking signs go up towards the southern end of the work zone and parking restored in the northern end of the work zone.

In each of the three work zones, travel lanes will be generally be reduced to one lane in each direction with restricted turns and from time to time you may expect flaggers to be operating one lane at a time. Please follow posted traffic signs.
Upcoming closures and major work
  • POSTPONED: Road closure at SW Oregon St and Delridge Way SW postponed to next week, October 16-19
    • Please note this work is highly weather-dependent and may change
    • Weekend work hours are from 9 AM Friday morning through 6 AM Monday morning. The roadway will be open before Monday morning traffic.
    • People traveling on Delridge Way SW will still be able to travel north and south past this intersection
    • People traveling to Delridge Way SW from the closed area will need to detour to SW Andover St via 21st Ave SW
    • Please refer to the King County Metro website for Metro bus detour routes for this closure
  • Pipework scheduled to begin next week near SW Juneau St
    • This work requires us to dig deep in the ground. Please anticipate noise, dust, and vibrations.
    • Intermittent, temporary water shut-offs may occur for select properties in late October. Seattle Public Utilities (SPU) will coordinate timing and residents will be notified in advance.
    • Driveways may be closed temporarily as crews complete this work. Residents will be notified in advance of any closures.
    • This work is expected to last for several weeks
  • Underground utility work to continue in late October in Zone C
    • Later this month we will return to the corridor to resume upgrading underground electric utilities in Zone C south of 21st Ave SW
    • This work will move south towards SW Henderson St and last for several weeks
  • Sidewalk closures and detours throughout Zone C
    • Next week, we will begin demolishing and rebuilding the sidewalk on the east side of Delridge Way SW near SW Orchard St
    • Demolition will last for approximately 1 week. Paving will immediately follow and last for 1 additional week.
    • Sidewalk work on the east side of Delridge Way SW between SW Thistle St and SW Trenton St will resume later this fall
    • Paving is weather-dependent and the schedule may change
Other project updates

Watch: Community meeting about adjacent Delridge Neighborhood Greenway 
A community meeting was held on Wednesday, October 7 to collect input on the diverters originally planned on 26th Ave SW at SW Brandon St and SW Genesee St. If you couldn't attend the meeting, you can watch a recording here.

REMINDER:
A survey to collect feedback on the diverters will remain open through OCtober 14. Learn more on our webpage.

Clarification: Roadway redesign near the Youngstown Cultural Arts Center at SW Genesee St
Last week, we shared an update on the roadway design near the Youngstown Cultural Arts Center in order to preserve several trees along the corridor. This redesign is not an overall reduction of the number of traffic lanes but rather a lane width reduction to allow for the trees to remain in place. Lanes will be 10.5 feet wide instead of the original 12 feet wide. The design also includes a reduction in the size of the planted median. Additionally, we were able to extend the curb next to the trees even further than previously, which is better for tree health.
Ongoing closures and work
  • Ongoing major pipework near SW Brandon St
    • Pipe testing for this work will begin as early as October 13 and will last through the end of the week. There are no anticipated interruptions to service as a result of this work.
    • Final pipe connections will take place in late October and will take approximately one day to complete
    • This work requires us to dig deep in the ground. Please anticipate noise, dust, and vibrations.
  • Continued temporary driveway impacts and closures throughout Zones A, B, and C during roadway and sidewalk upgrades
    • Expect intermittent impacts to driveway access. Residents will be notified in advance of any driveway closures.
    • We will work our way south in each section and may flip sides on Delridge Way SW. Please continue reading for more details.
Anticipated schedule changes due to wet weather this year
This fall, we will continue demolishing and repaving the roadway, driveways and sidewalks throughout the project corridor. Due to the wet weather, we may need to make last minute schedule changes to paving activities which may include delaying paving activities or starting concrete paving pours as the weather allows.

As a reminder, we aim to maintain access to driveways during demolition, which can last between 1 to 2 weeks in each area. If weather allows, paving will follow and typically require driveway closures for up to 1 week. Continue reading to learn more about our demolition and paving work zones and schedule.

Please plan for these schedule changes and reach out to us if you have any accessibility concerns during this work. You can learn more about typical paving impacts at the bottom of this email. Thank you for your patience during construction.
Our schedule is subject to change. Please sign up for our text message updates by texting DELRIDGE to 33222 to receive the most up to date information on night work and closures.
If you experience issues with your water service during construction, please contact Seattle Public Utilities’ 24/7 service line at (206) 386-1800.
If you have concerns about accessibility or other impacts of construction, please send us your address, contact information, and concerns so that we can better understand and work together throughout construction. You can reach us at DelridgeTransit@Seattle.gov or call 206-775-8739.
New work by zone
  • Zone A (West Seattle Bridge to SW Findlay St)
    • Continued demolition and paving work on Delridge Way SW (east side)
      • Paving between SW Genesee St and SW Oregon St is scheduled to be completed next week
      • Sidewalk pours will begin on the east side of Delridge Way SW between SW Charlestown St and SW Dakota St next week
    • Upcoming demolition and paving work on the west side of Delridge Way SW
      • We are continuing to demolish and repave the roadway on the west side of Delridge Way SW between SW Edmunds St and SW Hudson St
        • Paving along this stretch will continue through this week and intermittently next week. Please anticipate schedule changes if there is wet weather in the forecast.
        • Driveways will be closed to allow concrete to cure and provide access for crews to work in the area. Impacted residents will be notified of the updated schedule.
      • This week, we began demolishing the roadway between SW Hudson St and Puget Blvd SW on the west side
        • Expect intermittent driveway impacts while we are working in front of your driveway. Gravel ramps and/or steel plates will be in place to maintain access when work is not occurring.
        • We will begin repaving the roadway as early as October 13. Driveways will be closed for several days while the poured concrete cures.
        • This work is weather-dependent and subject to change
  • Zone B (SW Findlay St to north of SW Orchard St)
    • Storm work to begin at SW Willow St this Friday, October 9 and will last approximately one week
    • Storm work at SW Myrtle St to begin as early as Wednesday, October 7 and will last through mid-October
    • Roadway demolition and paving work to start in this section beginning in late October
      • We will begin work on the west side of Delridge Way SW between SW Graham St to 22nd Ave and then move between 22nd Ave to SW Holly St
  • Zone C
    • Sidewalk work beginning at the northeast corner of SW Orchard St next week. We will pour the sidewalk and driveways as early as October 19.
    • Underground utility work to continue in late October in Zone C

What to expect during paving 
As we begin paving near residential properties, you may experience impacts to your driveway as we demolish and restore the roadway in front of your property. During this work, you can expect: 

  • Temporary access restrictions in and out of driveways on Delridge Way SW during active demolition. Demolition work is usually limited to a few hours. 
  • Loud hammering, dust and vibrations 
  • During active demolition, onsite crews will be able to provide access to emergency vehicles or for people leaving their homes for emergencies 
  • If you need your car in a timely manner, we recommend parking on side streets. Otherwise, please be prepared for delays and plan to connect with crews onsite to coordinate access. 
  • Steel plates or a gravel ramp will be placed to provide access to the driveways outside of active work hour
  • Up to one week of driveway restrictions as concrete cures directly in front of your property. We will deliver notices to any properties with this impact.
  • Impacted properties will be notified in advance of this work occurring. 
What to expect during construction
Generally, we anticipate working weekdays between 7 AM and 7 PM.  Impacts will include:
  • Noise, dust, and large vehicle traffic
  • Temporary construction parking restrictions for weeks at a time
  • Periodic traffic detours
  • Vehicle lane shifts around work zones
  • Temporary utility service impacts
  • Flaggers to help direct traffic
  • Temporary bus detours and bus stop relocations
As part of this project, we will be upgrading the road condition throughout the corridor. You can expect roadway demolition to look like the photo above.
Project schedule
Stay updated
West Seattle High-Rise Bridge Safety Project
The closure of the West Seattle Bridge has impacted access to the Delridge community and how we all get around. Our Delridge Way SW – RapidRide H Line team is committed to keeping streets open and moving as much as possible and doing everything we can to minimize additional disruptions caused by construction and paving. Learn more about the
West Seattle High-Rise Bridge Safety project and sign up for email alerts to get the latest about the bridge.
 
If you have questions about the West Seattle High-Rise Bridge project, please contact their team by:
Phone: 206-684-7623
Email: 
684-Road@seattle.gov
 If you need this information translated, please call (206) 775-8739.
تحية طيبة, اذا احتجتم لترجمة هذه المعلومات ,الرجاء الاتصال على الرق  206-775-8739 

ይህንን መረጃ እንዲተረጉሙ ከፈለጉ ፣ እባክዎን በሚከተለው ቁጥር (206) 775-8739 ይደውሉ።
Yoo ooddefannon kun akka issinnif hiikammu barbaadan maallo bilbiilla kaanan bilbilla (206) 775-8739.
 
At the City of Seattle, we are continuing to follow guidance from federal, state, and local leaders and our public health partners regarding COVID-19. To keep our crews and the public safe, we have required all contractors to submit updated jobsite Health and Safety Plans to ensure that they comply with the safety and social distancing requirements in the Governor’s Order.
Copyright © 2020 Seattle Department of Transportation, All rights reserved.

Our mailing address is:
Address: 700 5th Ave, Suite 3800, Seattle, WA, 98104
Mailing Address: PO Box 34996, Seattle, WA, 98124-4996
Phone: 206-684-7623


Want to change how you receive these emails?
You can
update your preferences or unsubscribe from this list.






This email was sent to <<Email Address>>
why did I get this?    unsubscribe from this list    update subscription preferences
RapidRide Expansion Program · 700 5th Ave · Seattle Municipal Tower · Seattle, WA 98104-5058 · USA

Email Marketing Powered by Mailchimp