Demolition and paving continue throughout the corridor
Construction started June 2020 and is expected to continue through 2022.

Please share this email with others who might be interested in receiving project information and construction updates, and feel free to get in touch with us if you have any questions.

You may sign up for email updates using this form.
Translations now available

Para leer esta alerta en Español, visite nuestro sitio web del proyecto

Para basahin ang update na ito sa Tagalog, bisitahin ang aming website para sa proyekto

Để đọc email cập nhật này bằng Tiếng Việt, hãy truy cập trang web dự án của chúng tôi
Maxaad filan kartaa waqtiga dhismuhu socodo
 
Our schedule is subject to change. Please sign up for our text message updates by texting DELRIDGE to 33222 to receive the most up to date information on night work and closures.
REMINDER: Businesses along the corridor are open during this work. Please follow posted detour signs as you visit these businesses.
What to expect the week of November 9
We are currently working in all three zones at the same time, from north to south on Delridge Way SW. As our work zones shift you will see No Parking signs go up throughout the corridor. We will restore parking when possible as work is completed in an area.

In each of the three work zones, travel lanes will be generally be reduced to one lane in each direction with restricted turns and from time to time you may expect flaggers to be operating one lane at a time. Please follow posted traffic signs.

Please note that crews will not be working Wednesday, November 11.
Upcoming closures and major work
  • Demolition and paving now happening in Zone B
    • Crews have started demolishing the roadway on the west side of Delridge Way SW between SW Graham St to 22nd Ave SW
      • During this work, 23rd Ave SW will be closed at Delridge Way SW. People wanting to access Delridge Way SW from this neighborhood are encouraged to detour to SW Willow St. Please follow the detour map below.
    • Once demolition is complete, lanes will be poured beginning as early as November 12. Lane closures will be in place while we complete this work.
    • When demolition in this area is complete, we will move between 22nd Ave SW and SW Holly St to begin demolishing the road as soon as November 12
  • Sidewalk, ramp, and curb demolition and paving between SW Andover St and SW Alaska St beginning as early as November 9
    • As a reminder, sidewalks will be completely closed when concrete is being poured and while it cures
    • This work will last for several weeks
    • Residents and businesses will be notified in advance if their access will be restricted
  • Demolition and paving between SW Hudson St and Puget Blvd SW to begin as early as November 9
    • Demolition is expected to last for approximately a week and a half, during which driveway access will be maintained, except when we are demolishing directly in front of your driveway
    • SW Hudson St is currently closed for this work
    • Paving is scheduled to begin as early as November 16. Driveways will be closed until paving is complete.
    • Residents and businesses will be notified in advance if their access will be restricted by this work
23rd Ave SW Detour Map
Ongoing closures and work
  • Duct bank work continues in Zone C through the end of November
    • We are working with multiple agencies to install utilities in the trench along Delridge Way SW. You can expect sidewalk closures and shifted traffic lanes during this work.
    • We are currently working near SW Kenyon St and will continue working our way south towards SW Thistle St. This work will involve some intermittent driveway impacts. Residents will be notified in advance of their access being restricted.
  • Continued temporary driveway impacts and closures throughout Zones A, B, and C during roadway and sidewalk upgrades
    • Expect intermittent impacts to driveway access during demolition. Residents will be notified in advance of any driveway closures.
    • We will work our way south in each section and may flip sides on Delridge Way SW. Please continue reading for more details.
Anticipated schedule changes due to wet weather this year
This fall, we will continue demolishing and repaving the roadway, driveways and sidewalks throughout the project corridor. Due to the wet weather, we may need to make last minute schedule changes to paving activities which may include delaying paving activities or starting concrete paving pours as the weather allows.

As a reminder, we aim to maintain access to driveways during demolition, which can last between 1 to 2 weeks in each area. If weather allows, paving will follow and typically require driveway closures for up to 1 week. Continue reading to learn more about our demolition and paving work zones and schedule.

Please plan for these schedule changes and reach out to us if you have any accessibility concerns during this work. You can learn more about typical paving impacts at the bottom of this email. Thank you for your patience during construction.
If you experience issues with your water service during construction, please contact Seattle Public Utilities’ 24/7 service line at (206) 386-1800.
If you have concerns about accessibility or other impacts of construction, please send us your address, contact information, and concerns so that we can better understand and work together throughout construction. You can reach us at DelridgeTransit@Seattle.gov or call 206-775-8739.
Side street closures during demolition and paving
As we move along the corridor, there will be instances when we will need to demolish and rebuild the roadway in front of side streets. During this time, you can expect no access to or from Delridge Way SW. We will notify residents if there are any anticipated restrictions to specific properties. While we complete this work, please continue parking in designated parking spots along the street or in personal driveways if applicable. People who park their vehicles in the right-of-way near road closure signs or temporary no parking signs are subject to ticketing or towing.
New work by zone
  • Zone A (West Seattle Bridge to SW Findlay St)
    • Continued demolition and paving work on Delridge Way SW (east side)
      • Paving between SW Alaska St to SW Edmunds St is scheduled to continue into next week
        • As a reminder, driveways will be completely closed when concrete is being poured during paving
        • Residents and businesses will be notified in advance if their access will be restricted
      • Demolition between SW Edmunds St and SW Hudson St to continue through the end of this week. Paving scheduled to begin as early as November 9.
        • Access to driveways will be maintained during demolition and before paving, except when we are demolishing directly in front of your driveway
        • We will notify residents of driveway closures before paving begins
      • Demolition and paving between SW Hudson St and Puget Blvd SW to begin as early as November 9
        • Demolition is expected to last for approximately a week and a half, during which driveway access will be maintained, except when we are demolishing directly in front of your driveway
        • Paving is scheduled to begin as early as November 16. Driveways will be closed until paving is complete.
        • Residents and businesses will be notified in advance if their access will be restricted by this work
      • Demolition and paving between Puget Blvd SW and SW Brandon St to begin as early as November 18
  • Zone B (SW Findlay St to north of SW Orchard St)
    • Pipework will continue between 24th Ave SW and SW Myrtle St through mid-November
    • Roadway demolition and paving work continues in this section next week
      • We will continue work on the west side of Delridge Way SW between SW Graham St to 22nd Ave SW and then move between 22nd Ave SW to SW Holly St
      • 23rd Ave SW will be fully closed to traffic during this work. People wanting to access Delridge Way SW from this neighborhood are encouraged to detour to SW Willow St. 
      • Flaggers will be in the area to help control traffic
  • Zone C
    • Duct bank work has resumed and will continue in this area for several weeks

What to expect during paving 
As we begin paving near residential properties, you may experience impacts to your driveway as we demolish and restore the roadway in front of your property. During this work, you can expect: 

  • Temporary access restrictions in and out of driveways on Delridge Way SW during active demolition
  • Loud hammering, dust and vibrations 
  • During active demolition, onsite crews will be able to provide access to emergency vehicles or for people leaving their homes for emergencies 
  • If you need your car in a timely manner, we recommend parking on side streets. Otherwise, please be prepared for delays and plan to connect with crews onsite to coordinate access. 
  • Steel plates or a gravel ramp will be placed to provide access to the driveways outside of active work hour
  • Up to one week of driveway restrictions as concrete cures directly in front of your property. We will deliver notices to any properties with this impact.
  • Impacted properties will be notified in advance of this work occurring
What to expect during construction
Generally, we anticipate working weekdays between 7 AM and 7 PM.  Impacts will include:
  • Noise, dust, and large vehicle traffic
  • Temporary construction parking restrictions for weeks at a time
  • Periodic traffic detours
  • Vehicle lane shifts around work zones
  • Temporary utility service impacts
  • Flaggers to help direct traffic
  • Temporary bus detours and bus stop relocations
As part of this project, we will be upgrading the roadway throughout the corridor. The roadway above has been fully demolished and is getting prepared for paving. Driveways will be closed as we repave the roadway. You can expect roadway demolition to look like the photo above.
Project schedule
Stay updated
West Seattle High-Rise Bridge Safety Project
The closure of the West Seattle Bridge has impacted access to the Delridge community and how we all get around. Our Delridge Way SW – RapidRide H Line team is committed to keeping streets open and moving as much as possible and doing everything we can to minimize additional disruptions caused by construction and paving. Learn more about the
West Seattle High-Rise Bridge Safety project and sign up for email alerts to get the latest about the bridge.
 
If you have questions about the West Seattle High-Rise Bridge project, please contact their team by:
Phone: 206-400-7511
Email: 
westseattlebridge@seattle.gov
 If you need this information translated, please call (206) 775-8739.
تحية طيبة, اذا احتجتم لترجمة هذه المعلومات ,الرجاء الاتصال على الرق  206-775-8739 

ይህንን መረጃ እንዲተረጉሙ ከፈለጉ ፣ እባክዎን በሚከተለው ቁጥር (206) 775-8739 ይደውሉ።
Yoo ooddefannon kun akka issinnif hiikammu barbaadan maallo bilbiilla kaanan bilbilla (206) 775-8739.
 
At the City of Seattle, we are continuing to follow guidance from federal, state, and local leaders and our public health partners regarding COVID-19. To keep our crews and the public safe, we have required all contractors to submit updated jobsite Health and Safety Plans to ensure that they comply with the safety and social distancing requirements in the Governor’s Order.
Copyright © 2020 Seattle Department of Transportation, All rights reserved.

Our mailing address is:
Address: 700 5th Ave, Suite 3800, Seattle, WA, 98104
Mailing Address: PO Box 34996, Seattle, WA, 98124-4996
Phone: 206-684-7623


Want to change how you receive these emails?
You can
update your preferences or unsubscribe from this list.






This email was sent to <<Email Address>>
why did I get this?    unsubscribe from this list    update subscription preferences
RapidRide Expansion Program · 700 5th Ave · Seattle Municipal Tower · Seattle, WA 98104-5058 · USA

Email Marketing Powered by Mailchimp