No work happening between November 26-29. Work resumes Monday, November 30.

Continue reading to learn about our updated demolition and paving schedules for next week.

Construction started June 2020 and is expected to continue through 2022.
Translations now available

Para leer esta alerta en Español, visite nuestro sitio web del proyecto

Para basahin ang update na ito sa Tagalog, bisitahin ang aming website para sa proyekto

Để đọc email cập nhật này bằng Tiếng Việt, hãy truy cập trang web dự án của chúng tôi
Maxaad filan kartaa waqtiga dhismuhu socodo
 
Our schedule is subject to change. Please sign up for our text message updates by texting DELRIDGE to 33222 to receive the most up to date information on night work and closures.
Construction updates for the week of November 30

Please continue reading to learn about current and upcoming side street closures as well as work beginning the week of November 30. For a complete summary of the work currently happening in the corridor, please refer to our email update from last week.

Please note that we will not be working Thursday, November 26 to Sunday, November 29. Work will resume at 7 AM on Monday, November 30.

Our construction schedule is weather-dependent and dates may change. Thank you for your patience.
Major construction updates
  • Side street closures on the east side of Delridge Way SW during demolition and paving
    • Currently closed (timing is weather dependent and may change):
      • SW Alaska St (reopening date not yet determined; thank you for your patience)
      • SW Hudson St (reopening as early as next week)
      • 23rd Ave SW (reopening as early as next week)
      • Puget Blvd SW near the Delridge P-Patch Community Gardens (through the end of roadway paving)
    • Closing soon (timing is weather dependent and subject to change)
      • SW Willow St (closing as early as November 30)
      • SW Brandon St (closing when SW Hudson reopens)
      • SW Thistle St (closing as early as December 7)
  • Sidewalk demolition and paving continues on the east side of Delridge Way SW between SW Andover and SW Oregon St
    • Please follow posted signs for detours during this work. We encourage people walking to travel on the west side of Delridge Way SW.
    • To cross Delridge Way SW in this area, we encourage people walking to cross at SW Alaska St, SW Genesee St, or SW Oregon St
  • RESCHEDULED: Vehicle detection installation in the pavement and concrete work at the intersection of SW Oregon St and Delridge Way SW begins as early as December 7
    • Work will last approximately one week. Delridge Way SW will remain open during this work.
    • Traffic will be shifted to the east side of Delridge Way SW during this work
    • Sidewalks in this area will be reopened to accommodate the traffic shift as part of this work
  • Demolition on the east side between Puget Blvd SW and SW Brandon St continues into early next week
    • Paving is scheduled to begin as early as December 2. Driveways will be closed until paving is complete.
    • We will notify residents in advance of this work occurring
  • Demolition on the east side between SW Brandon St and SW Findlay St to begin as early as November 30
    • Demolition is expected to last for approximately one week
    • Paving is scheduled to start as early as December 12
  • Pipework to resume at SW Juneau St
    • We will begin working near SW Juneau St again as early as December 4. This work will continue for several weeks.
    • Please expect noise, dust, and vibrations during this work. If you experience with your water service, please contact Seattle Public Utilities' 24/7 service line at (206) 386-1800.
  • Paving on the west side between SW Graham St and 22nd Ave SW continues into next week
    • Driveways should open the week of December 7
    • 23rd Ave SW will also open when this work is complete
  • Demolition on the west side between SW Holly St and SW Willow St to begin as early as November 30
    • SW Willow St will be closed as part of this work beginning as early as November 30
    • People driving are encouraged to detour to 23rd Ave SW or SW Myrtle St
    • Paving is scheduled to begin in early December
  • Electrical work happening in the sidewalk between SW Orchard St and 21st Ave SW
    • We are currently demolishing sidewalks in this area to install and upgrade electrical utilities on the east side of Delridge Way SW
    • Paving is scheduled to begin in early December. Sidewalks are scheduled to reopen in mid-December.
    • People walking are encouraged to cross Delridge Way SW at SW Holden St or SW Orchard St. Please follow posted signage.
Side street closures during demolition and paving
As we move along the corridor, there will be instances when we will need to demolish and rebuild the roadway in front of side streets. During this time, you can expect no access to or from Delridge Way SW. We will notify residents if there are any anticipated restrictions to specific properties.

NOTICE: Parking restrictions during side street closures and construction
While we complete this work, please continue parking in designated parking spots along the street or in personal driveways if applicable. People who park their vehicles near No Parking signs (temporary or permanent), in the right-of-way near road closure signs, or near driveway and alley entrances are subject to ticketing or towing. This includes parking on narrow streets such as SW Edmunds St, Cottage Pl SW, and 22nd Ave SW near Longfellow Creek.

Safety is our top priority and we need to maintain access to neighborhoods for emergency vehicles.
REMINDER: Businesses along the corridor are open during this work. Please follow posted detour signs as you visit these businesses.
If you have concerns about accessibility or other impacts of construction, please send us your address, contact information, and concerns so that we can better understand and work together throughout construction. You can reach us at DelridgeTransit@Seattle.gov or call 206-775-8739.
As part of this project, we will be upgrading the roadway throughout the corridor. The roadway above has been partially demolished and is getting prepared for paving. Before paving, you can expect steel plates to be placed to provide access to your property when work is not occurring. Tarps will be placed if wet weather is in the forecast.
West Seattle High-Rise Bridge Safety Program
The closure of the West Seattle Bridge has impacted access to the Delridge community and how we all get around. Our Delridge Way SW – RapidRide H Line team is committed to keeping streets open and moving as much as possible and doing everything we can to minimize additional disruptions caused by construction and paving. Learn more about the
West Seattle High-Rise Bridge Safety project and sign up for email alerts to get the latest about the bridge.
 
If you have questions about the West Seattle High-Rise Bridge project, please contact their team by:
Phone: 206-400-7511
Email: 
westseattlebridge@seattle.gov
At the City of Seattle, we are continuing to follow guidance from federal, state, and local leaders and our public health partners regarding COVID-19. To keep our crews and the public safe, we have required all contractors to submit updated jobsite Health and Safety Plans to ensure that they comply with the safety and social distancing requirements in the Governor’s Order.
Copyright © 2020 Seattle Department of Transportation, All rights reserved.

Our mailing address is:
Address: 700 5th Ave, Suite 3800, Seattle, WA, 98104
Mailing Address: PO Box 34996, Seattle, WA, 98124-4996
Phone: 206-684-7623


Want to change how you receive these emails?
You can
update your preferences or unsubscribe from this list.






This email was sent to <<Email Address>>
why did I get this?    unsubscribe from this list    update subscription preferences
RapidRide Expansion Program · 700 5th Ave · Seattle Municipal Tower · Seattle, WA 98104-5058 · USA

Email Marketing Powered by Mailchimp