Construction resumes on Delridge Way SW
Construction started in June 2020 an is expected to continue through 2022.
Translations now available

Para leer esta alerta en Español, visite nuestro sitio web del proyecto

Para basahin ang update na ito sa Tagalog, bisitahin ang aming website para sa proyekto

Để đọc email cập nhật này bằng Tiếng Việt, hãy truy cập trang web dự án của chúng tôi
Maxaad filan kartaa waqtiga dhismuhu socodo
 
Project update
Construction schedule updates
This week, we have been working with limited crews onsite to continue the construction of the Delridge Way SW – RapidRide H Line project. We are working to reschedule construction activities throughout the corridor after experiencing the pause last week and wet weather this week. We are working as quickly as possible to help upgrade Delridge Way SW for all users and prepare it for the launch of RapidRide H Line service in 2022.

Throughout the winter, you can continue to expect updates from us as we continue to reschedule construction activities as weather allows. We will not be working on December 25 and January 1.

Update on RapidRide H Line from King County Metro
RapidRide H Line is now scheduled to begin service in 2022 (originally scheduled for September 2021) to ensure substantial construction completion and a smooth launch of service. RapidRide H Line continues to be a priority for Metro despite the economic impact the COVID-19 pandemic has had on Metro’s budget and time needed to reach 100% project design. A more detailed construction schedule will be available after a contractor is selected in the coming months. 

More information can be found on
King County Metro’s website.
Work by zone
Click the links below to learn about work happening in your zone.
Our schedule is subject to change. Please sign up for our text message updates by texting DELRIDGE to 33222 to receive the most up to date information on night work and closures.
Upcoming major construction updates
  • Side street closures on the east side of Delridge Way SW during demolition and paving
    • Currently closed (timing is weather dependent and may change):
      • SW Edmunds St (local access only)
      • SW Brandon St (closed into early next year)
      • SW Willow St (closed through the end of the year)
    • Closing soon (timing is weather dependent and subject to change)
      • SW Myrtle St (closed when SW Willow St reopens, as early as December 28)
      • SW Thistle St (closing in early 2021)
  • Driveways on the east side of Delridge Way SW between SW Alaska St and SW Hudson St to be reopened this week
  • Temporary street closure at SW Thistle St between Delridge Way SW and 20th Ave SW beginning as early as January 4
    • This street closure is required to complete temporary signal work and to demolish and rebuild the sidewalk as part of the duct bank work
    • This work is expected to last for several weeks
    • SW Thistle St will be local access only with no through access to Delridge Way SW
    • Select driveways will experience intermittent access restrictions during demolition and will also be fully closed during restoration work
  • Roadway and sidewalk demolition and paving starting soon in Zone C
    • Roadway demolition is scheduled to begin on the east side of Delridge Way SW between SW Trenton St and SW Henderson St as early as December 21 with paving to follow in the new year
    • Sidewalk demolition between SW Cloverdale St and SW Trenton St to begin as early as December 23
      • We will upgrade utilities in the sidewalk. Access to driveways will be temporarily restricted during this work.
      • Demolition is expected to last for several weeks
    • Roadway demolition is scheduled to begin on the west side of Delridge Way SW between SW Henderson and 20th Ave SW as early as January 4 with paving to follow
      • Access to businesses will be maintained
Work by zone
For all work described below, residents and businesses will be notified in advance of any anticipated impacts.
  • Zone A (West Seattle Bridge to SW Findlay St)
    • Sidewalk, ramp and curb demolition, and paving on the east side of Delridge Way SW between SW Andover St and SW Oregon St to continue through the end of the year
      • As a reminder, sidewalks will be completely closed when concrete is being poured and while it cures
      • Bus pads and foundations will also be formed as a part of this work
      • The stairs at SW Genesee St and Delridge Way SW will be closed during working hours and for one additional full day while concrete cures
        • Detour signs will be posted when the staircase is closed
        • We recommend that pedestrians wishing to access Delridge Way SW travel to SW Andover St instead
      • For people wanting to travel on Delridge Way SW on an ADA accessible path from the Youngstown Cultural Arts Center, please follow the delineated detour in our work zone in the northbound travel lanes. When work is happening in the area, spotters will be available to assist individuals to the pedestrian crossing at SW Genesee St or the pedestrian bridge at SW Oregon St.
        • This sidewalk is scheduled to be reopened soon. Thank you for your patience.
    • Electrical upgrades at the bus stop on the west side of SW Andover St
      • Demolition and upgrades are scheduled to begin this week and will last into early next year
      • Work is limited to the sidewalk where the bus stop is, but crews will be in the street to complete this work
    • RESCHEDULED: Vehicle-detection loop installation and concrete work at the intersection of SW Oregon St and Delridge Way SW beginning as early as December 28
      • This loop will help detect vehicles making turns at this intersection
      • This work is expected to last for approximately one week
      • The intersection will remain open throughout this work. People driving will experience a new traffic pattern in this area during this work. Please follow posted signs when driving through the area.
        • During the vehicle-detection loop installation, northbound and southbound traffic will be split in the roadway
        • After installation is complete, all traffic will be shifted to the east side of the roadway
    • Driveway demolition and restoration on the east side of Delridge Way SW between SW Alaska St and SW Hudson St to be completed this week
      • See above for details on our planned schedule
    • Continued demolition and paving on Delridge Way SW (east side)
      • Paving in Zone A has been rescheduled and driveways will be fully reopened soon in the following areas:
        • SW Hudson to Puget Blvd SW (open by the end of this week)
        • Puget Blvd SW and SW Brandon St (open by the end of next week)
    • Demolition between SW Brandon St and SW Findlay St continues next week
      • Paving is scheduled to begin as early as December 28
         
  • Zone B (SW Findlay St to north of SW Orchard St)
    • Roadway demolition and paving work continues on the west side of Delridge Way SW in this section
      • Paving between SW Graham St and 22nd Ave SW completed
        • Crews will return to this area as early as December 21 to begin pouring curbs. This work will last for approximately two weeks with no anticipated impacts to driveways or residences.
      • Paving between 22nd Ave SW and SW Holly St is complete
        • Crews will return to this area at a later date to pour curbs
      • Paving between SW Holly St and SW Willow St to continue through next week
        • Paving is scheduled to continue through next week. Driveways will reopen when paving is complete.
        • SW Willow St is closed as part of this work. People driving are encouraged to detour to 23rd Ave SW or SW Myrtle St.
      • Demolition between SW Willow St and SW Croft Pl continues into next week
        • Paving is scheduled to begin as early as December 28
      • Demolition between SW Croft Pl and SW Myrtle St to begin as early as December 28
        • Due to holidays and non-working days, demolition may last approximately two weeks
        • Paving is scheduled to begin in the new year
           
  • Zone C (SW Orchard St to SW Roxbury St)
    • Electrical work continues in the sidewalk between SW Orchard St and 21st Ave SW
      • We are currently demolishing sidewalks in this area to install and upgrade electrical utilities on the east side of Delridge Way SW
      • Paving is scheduled to begin in late December. Sidewalks are scheduled to reopen after paving is completed.
      • People walking are encouraged to cross Delridge Way SW at SW Holden St or SW Orchard St. Please follow posted signage.
    • Duct bank work and restoration to continue in this area for several weeks
      • Duct bank work on Delridge Way SW is nearly complete. We are now working to restore the sidewalks and roadway along Delridge Way SW.
        • As part of this work, sidewalk paving on the west side of Delridge Way SW between SW Kenyon St and SW Thistle St is scheduled to begin as early as December 28
        • This work will require driveways to be temporarily closed. Driveways are scheduled to reopen by January 1. Properties will be notified in advance.
    • Upcoming closure of SW Thistle St on the east side of Delridge Way SW as early as January 4
      • Parking will be restored after the duct bank installation and sidewalk work in this area is completed
    • Roadway demolition and paving work beginning on the east side of Delridge Way SW between SW Trenton St and SW Henderson St
      • Demolition is scheduled to begin as early as December 21 with paving to begin as early as January 4
    • Roadway demolition and paving work beginning on the west side of Delridge Way SW between SW Henderson and 20th Ave SW
      • Demolition is scheduled to begin as early as January 4 with paving to follow
    • Sidewalk demolition on the west side of Delridge Way SW between SW Cloverdale St and SW Trenton St to begin as early as December 23
      • We will begin demolishing the sidewalks in this area to install and upgrade electrical utilities on the east side of Delridge Way SW
      • This work will last for at least two weeks and will include intermittent driveway impacts
REMINDER: Businesses along the corridor are open during this work. Please follow posted detour signs as you visit these businesses.
If you have concerns about accessibility or other impacts of construction, please send us your address, contact information, and concerns so that we can better understand and work together throughout construction. You can reach us at DelridgeTransit@Seattle.gov or call 206-775-8739.
What to expect during paving and construction
  • Work hours are typically between 7 AM and 7 PM but can last until 10 PM without a noise variance
  • You may experience temporary access restrictions in and out of driveways on Delridge Way SW during active demolition
  • Loud hammering, dust, and vibrations
  • During active demolition, onsite crews will be able to provide access to emergency vehicles of for people leaving their homes for emergencies
  • If you need your car in a timely manner, we recommend parking on side streets. Otherwise, please be prepared for delays and plan to connect with crews onsite to coordinate access.
  • Steel plates or a gravel ramp will be placed to provide access to the driveways outside of active work hours
  • Up to one week of driveway restrictions as concrete cures directly in front of your property. We will deliver notices to any properties with this impact.
  • Vehicle lane shifts around work zones
  • Temporary bus detours and bus stop relocations. Please contact Metro for more information. 
As part of this project, we will be upgrading the roadway throughout the corridor. The roadway panel above has recently been formed. Installing forms takes approximately 1 day, followed by a day of pouring and several days of concrete curing for each roadway panel. Driveways will be temporarily closed during this work.
West Seattle High-Rise Bridge Safety Program
The closure of the West Seattle Bridge has impacted access to the Delridge community and how we all get around. Our Delridge Way SW – RapidRide H Line team is committed to keeping streets open and moving as much as possible and doing everything we can to minimize additional disruptions caused by construction and paving. Learn more about the
West Seattle High-Rise Bridge Safety program and sign up for email alerts to get the latest about the bridge.
 
If you have questions about the West Seattle High-Rise Bridge program, please contact their team by:
Phone: 206-400-7511
Email: 
westseattlebridge@seattle.gov
At the City of Seattle, we are continuing to follow guidance from federal, state, and local leaders and our public health partners regarding COVID-19. To keep our crews and the public safe, we have required all contractors to submit updated jobsite Health and Safety Plans to ensure that they comply with the safety and social distancing requirements in the Governor’s Order.
Copyright © 2020 Seattle Department of Transportation, All rights reserved.

Our mailing address is:
Address: 700 5th Ave, Suite 3800, Seattle, WA, 98104
Mailing Address: PO Box 34996, Seattle, WA, 98124-4996
Phone: 206-684-7623


Want to change how you receive these emails?
You can
update your preferences or unsubscribe from this list.






This email was sent to <<Email Address>>
why did I get this?    unsubscribe from this list    update subscription preferences
RapidRide Expansion Program · 700 5th Ave · Seattle Municipal Tower · Seattle, WA 98104-5058 · USA

Email Marketing Powered by Mailchimp