Campaign URL
Copy
Twitter
0
tweets
Subscribe
Past Issues
RSS
Translate
English
العربية
Afrikaans
беларуская мова
български
català
中文(简体)
中文(繁體)
Hrvatski
Česky
Dansk
eesti keel
Nederlands
Suomi
Français
Deutsch
Ελληνική
हिन्दी
Magyar
Gaeilge
Indonesia
íslenska
Italiano
日本語
ភាសាខ្មែរ
한국어
македонски јазик
بهاس ملايو
Malti
Norsk
Polski
Português
Português - Portugal
Română
Русский
Español
Kiswahili
Svenska
עברית
Lietuvių
latviešu
slovenčina
slovenščina
српски
தமிழ்
ภาษาไทย
Türkçe
Filipino
украї́нська
Tiếng Việt
Construction@Countway
Time-lapse cameras are back and the renovation is moving fast!
We are looking forward to the day we can show you in person.
December 18 - December 24
Thank you for subscribing!
Construction is close to being complete! Head to the Countway Renovation webpage for
time lapse videos
or
click on this link to read past issues
.
On the INSIDE
1st Floor
Cafe plumbing
Cafe mill work
Exterior door work (Huntington and Shattuck)
Furniture delivery / Set-up furniture
Removal of construction materials and equipment on L1
L1 Floor
Revise lighting at circulation desk
On the OUTSIDE
Travel Route Changes
Lower lever plaza closed at Huntington Avenue
Lower level plaza at Shattuck always accessed via temporary stairway
Stone stairs at Shattuck closed for renovation work
Stairs at Kresge always open
Huntington Ave. sidewalk and metered spots closed for sidewalk renovation-pedestrian traffic has moved to opposite side of Huntington Avenue
Concrete placements for new sidewalks
Work on marble balustrade (west side)
Shattuck Street bridge work
Construction Contacts
Questions about construction?
Fred Hagerty: fred_hagerty@hms.harvard.edu