No work between January 1-3
Construction started in June 2020 and is expected to continue through 2022.
Translations now available

Para leer esta alerta en Español, visite nuestro sitio web del proyecto

Para basahin ang update na ito sa Tagalog, bisitahin ang aming website para sa proyekto

Để đọc email cập nhật này bằng Tiếng Việt, hãy truy cập trang web dự án của chúng tôi
Maxaad filan kartaa waqtiga dhismuhu socodo
 
Project update
Construction continues this winter
This week, we welcomed back our all of our crews to the project corridor to resume construction activities. In Zone C, we were able to reschedule our demolition and paving activities to start this week as other work was completed ahead of schedule. This start date will allow us to finish work in this area sooner and we appreciate your flexibility as the construction schedule shifts. Thank you for your patience during construction.
Work by zone
Click the links below to learn about work happening in your zone.
Our schedule is subject to change. Please sign up for our text message updates by texting DELRIDGE to 33222 to receive the most up to date information on night work and closures.
Upcoming major construction updates
  • Side street closures on the east side of Delridge Way SW during demolition and paving
    • Currently closed (timing is weather dependent and may change):
      • SW Brandon St (closed through the end of this week)
      • SW Willow St (closed through early January)
    • Closing soon (timing is weather dependent and subject to change)
      • SW Myrtle St (closed as soon as SW Willow St reopens)
      • SW Thistle St (closing as early as January 4)
  • Vehicle detection loop installation and concrete work at the intersection of SW Oregon St and Delridge Way SW scheduled to begin as early as January 4
    • Traffic will be split around the planned roadway median during this work
    • The following week, we will begin shifting all traffic to the east side. Please follow posted signs for the new traffic pattern.
    • This work will last for approximately one week
  • Temporary street closure at SW Thistle St between Delridge Way SW and 20th Ave SW beginning as early as January 4
    • This street closure is required to complete temporary signal work and to demolish and rebuild the sidewalk as part of the duct bank work
    • This work is expected to last for several weeks
    • SW Thistle St will be local access only with no through access to Delridge Way SW
    • Select driveways will experience intermittent access restrictions during demolition and will also be fully closed during restoration work
  • Roadway demolition and paving to resume on the west side of Delridge Way SW in Zone A and on the east side of Delridge Way SW in Zone B
    • Continue reading below to find out where we will start working soon
Work happening this week and next week
For all work described below, residents and businesses will be notified in advance of any anticipated impacts. Dates for construction activities scheduled beyond the new year are subject to change depending upon weather.
  • Zone A (West Seattle Bridge to SW Findlay St)
    • Paving for sidewalks, ramps, and curbs on the east side of Delridge Way SW between SW Andover St and SW Oregon St to continue through the end of this week
      • The sidewalk will be fully reopened before traffic is split or shifted to the east side of Delridge Way SW
    • Electrical upgrades at the bus stop on the west side of SW Andover St
      • Demolition and upgrades are scheduled to begin this week and be completed late next week
    • Vehicle-detection loop installation and concrete work at the intersection of SW Oregon St and Delridge Way SW scheduled to begin as early as January 4
    • Curb ramp and crossing median installation at SW Dakota St to begin as early as January 4
      • This work will last approximately one week
      • People driving will follow a new traffic pattern in this area. Please follow the marked roadway.
    • Continued demolition and paving on Delridge Way SW (east side)
      • The remaining paving in Zone A is scheduled to be completed this week if weather allows:
        • Puget Blvd SW and SW Brandon St
        • SW Brandon St to SW Findlay St
        • SW Brandon St intersection
    • Continued demolition and paving on Delridge Way SW (west side)
      • Demolition to begin between Puget Blvd SW and SW Brandon St as early as January 6
        • Traffic will need to be shifted to the east side of Delridge Way SW before work can begin on the west side
        • Once demolition is complete, paving is scheduled to begin in late January
        • Access to businesses will be maintained during this work. Only one driveway at businesses will be impacted at any given time.
           
  • Zone B (SW Findlay St to north of SW Orchard St)
    • Curb installation happening throughout Zone B
      • As roadway paving is completed on each block, we will return to form and pour curbs throughout Zone B
      • This work will continue for several weeks. Driveways will not be impacted as a result of this work.
    • Roadway demolition and paving work continues on the west side of Delridge Way SW in this section
      • Paving between SW Holly St and SW Willow St to continues
        • Paving is scheduled to be completed soon. Driveways will reopen when paving is complete.
      • Paving between SW Willow St and SW Croft Pl continues this week and is scheduled to be completed next week
        • Crews will remain in the area to form and pour curbs next week after this work is complete
        • SW Willow St is closed as part of this work. People driving are encouraged to detour to 23rd Ave SW or SW Myrtle St.
      • Demolition between SW Croft Pl and SW Myrtle St continues into early next week
        • Paving is scheduled to begin as early as January 6
    • Roadway demolition and paving work begins on the east side of Delridge Way SW in Zone B
      • Demolition between SW Graham St and 22nd Ave SW scheduled to begin as early as January 6
        • Paving is scheduled to begin in mid-January
      • Demolition between 22nd Ave SW and SW Holly St to begin in late January
      • Traffic will be shifted around the completed and active work zones in Zone B. People driving are encouraged to practice caution when traveling through this area.
         
  • Zone C (SW Orchard St to SW Roxbury St)
    • Electrical work continues in the sidewalk between SW Orchard St and 21st Ave SW
      • Paving and restoration of the sidewalk is scheduled to begin next week
      • Pedestrians are encouraged to detour via SW Holden St or SW Orchard St while this work is happening
    • Sidewalk and driveway restoration between SW Kenyon St and SW Thistle St to continue for several weeks
      • This work will require select driveways to be temporarily closed. Driveways are scheduled to reopen late this week.
    • Upcoming closure of SW Thistle St on the east side of Delridge Way SW as early as January 4 for excavation and duct bank installation
      • This work will last for approximately two weeks, with paving and restoration to follow
      • Parking will be restored after the duct bank installation and sidewalk work in this area is completed
    • Updated dates for roadway and sidewalk demolition in Zone C
      • Demolition continues on the east side of Delridge Way SW between SW Trenton St and SW Henderson St
        • Paving to begin as early as January 8
      • Roadway demolition on the west side of Delridge Way SW between SW Henderson and 20th Ave SW began this week
        • Paving is scheduled to begin towards the end of next week
      • *CORRECTION* Sidewalk demolition on the east side of Delridge Way SW between SW Cloverdale St and SW Trenton St starting soon
        • In our email update last week, we said this work would be happening on the west side of Delridge Way SW. This was incorrect. Work will be happening on the east side of Delridge Way SW. We apologize for the confusion.
        • We will begin demolishing the sidewalks in this area to install and upgrade electrical utilities on the east side of Delridge Way SW
        • This work will last for at least two weeks and will include intermittent driveway impacts
REMINDER: Businesses along the corridor are open during this work. Please follow posted detour signs as you visit these businesses.
If you have concerns about accessibility or other impacts of construction, please send us your address, contact information, and concerns so that we can better understand and work together throughout construction. You can reach us at DelridgeTransit@Seattle.gov or call 206-775-8739.
What to expect during paving and construction
  • Work hours are typically between 7 AM and 7 PM but can last until 10 PM without a noise variance
  • You may experience temporary access restrictions in and out of driveways on Delridge Way SW during active demolition
  • Loud hammering, dust, and vibrations
  • During active demolition, onsite crews will be able to provide access to emergency vehicles of for people leaving their homes for emergencies
  • If you need your car in a timely manner, we recommend parking on side streets. Otherwise, please be prepared for delays and plan to connect with crews onsite to coordinate access.
  • Steel plates or a gravel ramp will be placed to provide access to the driveways outside of active work hours
  • Up to one week of driveway restrictions as concrete cures directly in front of your property. We will deliver notices to any properties with this impact.
  • Vehicle lane shifts around work zones
  • Temporary bus detours and bus stop relocations. Please contact Metro for more information. 
As part of this project, we will be upgrading the roadway throughout the corridor. The road above has recently been demolished. During demolition, crews will maintain access to driveways via steel plates like the ones above or via gravel ramp.
West Seattle High-Rise Bridge Safety Program
The closure of the West Seattle Bridge has impacted access to the Delridge community and how we all get around. Our Delridge Way SW – RapidRide H Line team is committed to keeping streets open and moving as much as possible and doing everything we can to minimize additional disruptions caused by construction and paving. Learn more about the
West Seattle High-Rise Bridge Safety program and sign up for email alerts to get the latest about the bridge.
 
If you have questions about the West Seattle High-Rise Bridge program, please contact their team by:
Phone: 206-400-7511
Email: 
westseattlebridge@seattle.gov
At the City of Seattle, we are continuing to follow guidance from federal, state, and local leaders and our public health partners regarding COVID-19. To keep our crews and the public safe, we have required all contractors to submit updated jobsite Health and Safety Plans to ensure that they comply with the safety and social distancing requirements in the Governor’s Order.

Thanks for reading!

Madison Linkenmeyer
Delridge Transit Outreach Team
delridgetransit@seattle.gov
206-775-8739
Copyright © 2020 Seattle Department of Transportation, All rights reserved.

Our mailing address is:
Address: 700 5th Ave, Suite 3800, Seattle, WA, 98104
Mailing Address: PO Box 34996, Seattle, WA, 98124-4996
Phone: 206-684-7623


Want to change how you receive these emails?
You can
update your preferences or unsubscribe from this list.






This email was sent to <<Email Address>>
why did I get this?    unsubscribe from this list    update subscription preferences
RapidRide Expansion Program · 700 5th Ave · Seattle Municipal Tower · Seattle, WA 98104-5058 · USA

Email Marketing Powered by Mailchimp