Copy
Greetings | تحية طيبة  | ሰላም I Nagga qaabaadha I Saludos | Salaamu caleykum I Pagbati I Chào bạn |
Intersection upgrades at SW Orchard St and Delridge Way SW continue for several weeks

Construction started in June 2020 and is expected to continue through 2022.
Translations now available

Para leer esta alerta en Español, visite nuestro sitio web del proyecto

Para basahin ang update na ito sa Tagalog, bisitahin ang aming website para sa proyekto

Để đọc email cập nhật này bằng Tiếng Việt, hãy truy cập trang web dự án của chúng tôi
Maxaad filan kartaa waqtiga dhismuhu socodo
 
Our schedule is subject to change. Please sign up for our text message updates by texting DELRIDGE to 33222 to receive the most up to date information on night work and closures. 
Ongoing intersection upgrades at SW Orchard St
For the next few weeks, we will continue to demolish and upgrade the intersection at SW Orchard St and Delridge Way SW. We will upgrade the entire intersection in phases. Each phase will take approximately 1 week to finish.

In order to shift traffic around the work zones, we will need to reduce travel to one lane in each direction on both Delridge Way SW and SW Orchard St. You can expect heavy traffic through this area while this work takes place. A uniformed police officer will be at the intersection to help people navigate through the area.



For information on potential bus reroutes, please visit King County Metro's website.
Major construction updates
Please continue reading below to learn details about this work. You can click on the zones to learn about work happening in your zone.
  • Ongoing side street closures on Delridge Way SW during demolition and paving
    • SW Hudson St (east side)
    • SW Findlay St (west side)
    • SW Juneau St (west side)
    • SW Thistle St (east side)
    • SW Myrtle St (temporary access restrictions during intersection upgrades at SW Orchard St)
  • Zone A (West Seattle Bridge to SW Findlay St)
    • Roadway upgrades on SW Hudson St between Delridge Way SW and 25th Ave SW continue (west side)
    • Upcoming mill and overlay roadway upgrades in Zone A between the West Seattle Bridge and SW Dakota St
  • Zone B (SW Findlay St to north of SW Orchard St)
    • Restoration between SW Willow St and SW Orchard St continues through April (east side)
    • Electrical upgrades on the corners of the intersection of SW Findlay St and Delridge Way SW to install new signal foundations
    • Paving between SW Juneau St and SW Graham St continues (west side)
  • Zone C (SW Orchard St to SW Roxbury St)
    • Intersection demolition and paving at SW Orchard St and Delridge Way SW continues into mid-May
    • Roadway upgrades at 21st Ave SW and Delridge Way SW continue
    • Intersection upgrades at SW Kenyon St resume next week
    • Bus stop upgrades beginning near SW Thistle St (west side)
Work happening this week and next week
For all work described below, residents and businesses will be notified in advance of any anticipated impacts. Dates for construction activities scheduled are subject to change depending upon weather.
  • Zone A (West Seattle Bridge to SW Findlay St)
    • Landscaping in Zone A continues
      • This week, we worked with our Urban Forestry team and their contractors to begin landscaping throughout Zone A
      • This work will require us to temporarily restrict parking near our work zones. Our work zones will be limited to the planting strips near sidewalks and the roadway median.
    • Upcoming demolition and paving on Delridge Way SW (east side)
      • Sidewalk and curb ramp upgrades continue in Zone A
        • We will continue upgrading sidewalks and curb ramps at SW Hudson St and Puget Blvd SW into early May
        • We will also begin building the median and pedestrian islands near Puget Blvd SW in late April
    • Upcoming demolition and paving on Delridge Way SW (west side)
      • Sidewalk upgrades throughout Zone A
        • We will continue upgrading the sidewalks and curb ramps near SW Brandon St through April
      • Roadway upgrades on the west side of SW Hudson St between Delridge Way SW and 25th Ave SW continue
    • Upcoming roadway upgrades in North Delridge
      • Beginning as early as the week of May 3, we will upgrade the roadway between the West Seattle Bridge and SW Dakota St
      • We will mill and overlay the roadway, which consists of grinding off the top layer of the roadway and replacing the surface
      • This method of upgrading roads is less noisy than traditional demolition and paving, though you should still anticipate noise, dust, and vibration during this work 
         
  • Zone B (SW Findlay St to north of SW Orchard St)
    • Bus stop upgrades in Zone B continue
      • Bus stop upgrades at SW Myrtle St will continue through the rest of this month
        • A bus island and bicycle bypass area will be installed as a part of this work
        • People driving should practice caution when driving around the new bus island
    • Continued demolition and paving on Delridge Way SW (east side)
      • Sidewalk restoration between SW Willow St and SW Orchard St to continue through April
        • Thank you for your patience during demolition
        • We will now work on installing curb ramps, sidewalks, and the roadway  median in this section
      • Paving between SW Juneau St and SW Graham St near the Louisa Boren STEM K-8 continues
        • We will continue paving the roadway in sections through the end of the next week
        • We will pour the remaining areas in front of driveways in early May. Residents will be notified in advance of this work.
           
  • Zone C (SW Orchard St to SW Roxbury St)
    • Intersection demolition and paving at SW Orchard St and Delridge Way SW
      • We finished working on the southeast section of the intersection this week
      • We will aim to complete one section of the intersection each week
      • This work is weather dependent and subject to change
      • Some of this work may occur overnight. A uniformed police officer will be present to help people navigate through this area at all times
    •  Bus stop upgrades in Zone C continue into May
      • Bus stop upgrades at SW Thistle St on the west side of Delridge Way SW rescheduled
        • We will begin demolishing the southwest corner of SW Thistle St in early May
        • This work will last for several weeks as we upgrade electrical utilities and rebuild the roadway, curb ramps, and sidewalks in this area
      • Bus stop upgrades at SW Trenton St on the west side of Delridge Way SW continue
        • We will pour the roadway, curb ramps, and sidewalks next week
        • This work will continue into May
  • Ongoing intersection upgrades at SW Kenyon St
    • SW Kenyon St intersection upgrades resume next week
      • The next phase of this work is scheduled to begin on April 16
      • A uniformed police officer will be stationed at the intersection at all times to help direct traffic
      • We will finish this work by the end of the week
  • Potholing for duct bank work resumes on Delridge Way SW
    • Utility, sidewalk, and driveway upgrades will last for several weeks
  • Roadwork near 21st Ave SW continues
    • Paving in this section will continue for several more weeks
      • We will shift traffic around our work zones as each lane is poured and cured
    • We will remain in the area for several more weeks to upgrade stormwater utilities and install curbs
    • In early May, we will begin pouring concrete at the new RapidRide station
    • We are also planning to rebuild the intersection where 21st Ave SW meets Delridge Way SW
      • Demolition and paving will occur in May
      • 21st Ave SW will be fully closed during this time
Contact information for local utility providers and services
Seattle Public Utilities 24/7 Emergency Line:
206-386-1800
Seattle Public Utilities - Missed trash collection: Report online
Puget Sound Energy - Gas leak: 1-888-225-5773
Seattle City Light - Report a power outage: 206-684-3000
USPS Westwood Post Office: 206-938-7769
If you have concerns about accessibility or other impacts of construction, please send us your address, contact information, and concerns so that we can better understand and work together throughout construction. You can reach us at DelridgeTransit@Seattle.gov or call 206-775-8739.
A uniformed police officer will be present at the intersection of SW Orchard St and Delridge Way SW while upgrades take place over the next several weeks. Please follow the directions given by the officer as you navigate the work zone.  
REMINDER: Businesses along the corridor are open during this work. Please follow posted detour signs as you visit these businesses.
At the City of Seattle, we are continuing to follow guidance from federal, state, and local leaders and our public health partners regarding COVID-19. To keep our crews and the public safe, we have required all contractors to submit updated jobsite Health and Safety Plans to ensure that they comply with the safety and social distancing requirements in the Governor’s Order.

Thanks for reading!

Madison Linkenmeyer
Delridge Transit Outreach Team
delridgetransit@seattle.gov
206-775-8739
Copyright © 2020 Seattle Department of Transportation, All rights reserved.

Our mailing address is:
Address: 700 5th Ave, Suite 3800, Seattle, WA, 98104
Mailing Address: PO Box 34996, Seattle, WA, 98124-4996
Phone: 206-684-7623


Want to change how you receive these emails?
You can
update your preferences or unsubscribe from this list.






This email was sent to <<Email Address>>
why did I get this?    unsubscribe from this list    update subscription preferences
RapidRide Expansion Program · 700 5th Ave · Seattle Municipal Tower · Seattle, WA 98104-5058 · USA

Email Marketing Powered by Mailchimp