Copy
Greetings | تحية طيبة  | ሰላም I Nagga qaabaadha I Saludos | Salaamu caleykum I Pagbati I Chào bạn |
Full intersection closure at 21st Ave SW and Delridge Way SW for roadway upgrades
Construction started in June 2020 and is expected to continue through 2022.
Translations now available

Para leer esta alerta en Español, visite nuestro sitio web del proyecto

Para basahin ang update na ito sa Tagalog, bisitahin ang aming website para sa proyekto

Để đọc email cập nhật này bằng Tiếng Việt, hãy truy cập trang web dự án của chúng tôi
Maxaad filan kartaa waqtiga dhismuhu socodo
 
Our schedule is subject to change. Please sign up for our text message updates by texting DELRIDGE to 33222 to receive the most up to date information on night work and closures. 
Full intersection closure at 21st Ave SW and Delridge Way SW
21st Ave SW is closed to through-traffic for roadway demolition and paving. This area is expected to reopen in mid-May. People driving should detour to SW Trenton St or SW Orchard St during these upgrades.
The slip lane (in yellow) will be local access only for residents adjacent to the road. There will be no access to 21st Ave SW from this area.
Major construction updates
Please continue reading below to learn details about this work. You can click on the zones to learn about work happening in your zone.
  • Ongoing side street closures on Delridge Way SW during demolition and paving
    • SW Thistle St (east side)
    • 21st Ave SW
  • Zone A (West Seattle Bridge to SW Findlay St)
    • Repairs and roadway upgrades in Zone A between the West Seattle Bridge and SW Dakota St
    • Landscaping continues throughout Zone A
  • Zone B (SW Findlay St to north of SW Orchard St)
    • Restoration between SW Willow St and SW Orchard St continues (east side)
    • Electrical upgrades on the corners of the intersection of SW Findlay St and Delridge Way SW to install new signal foundations
  • Zone C (SW Orchard St to SW Roxbury St)
    • Intersection demolition and paving at SW Orchard St and Delridge Way SW continues into mid-May
    • 21st Ave SW and Delridge Way SW intersection closed for roadway upgrades
    • Bus stop upgrades continue near SW Thistle St and SW Trenton St (west side)
Work happening this week and next week
For all work described below, residents and businesses will be notified in advance of any anticipated impacts. Dates for construction activities scheduled are subject to change depending upon weather.
  • Zone A (West Seattle Bridge to SW Findlay St)
    • Roadway upgrades continue in North Delridge
      • This week, we finished milling the roadway between the West Seattle Bridge and SW Dakota St
        • Please drive carefully on the rough pavement and be aware of any raised castings
      • Beginning the week of May 17, we will begin sealing cracks in the milled roadway
      • Asphalt overlay paving is scheduled to begin as early as May 24
        • This work will take place from 7 PM to 7 AM
        • Access to driveways will be restricted for a few hours while the asphalt cools. Residents and businesses will be notified in advance of any major driveway impacts.
    • Sidewalk and curb ramp upgrades continue throughout Zone A
      • For the next few weeks, we will continue upgrading sidewalks and curb ramps in the following areas:
        • Eastern curb ramps at Puget Blvd SW through the end of this week
        • Median and pedestrian islands near Puget Blvd SW will be completed in mid-May
        • Sidewalks on the west side of Delridge Way SW near SW Brandon St through next week
        • Sidewalks on the west side of SW Hudson St and the east side of SW Brandon St to start next week
           
  • Zone B (SW Findlay St to north of SW Orchard St)
    • Electrical utility upgrades at the intersection of SW Findlay St and Delridge Way SW
      • We will work on the corners of this intersection to install new signal foundations
      • This work will continue into May
    • Continued demolition and paving on Delridge Way SW (east side)
      • Sidewalk restoration between SW Willow St and SW Orchard St to continue through the end of next week
        • We will continue installing curb ramps, sidewalks, and the roadway median in this section
           
  • Zone C (SW Orchard St to SW Roxbury St)
    • Intersection demolition and paving at SW Orchard St and Delridge Way SW nearly complete
      • Next week, we will upgrade the final quadrant of the intersection
      • This work is weather dependent and subject to change
      • Some of this work may occur overnight
    • 21st Ave SW and Delridge Way SW intersection closed for roadway upgrades
      • Demolition started this week and will continue into early next week
        • Driveways will be closed while this work takes place
        • Impacted residents will be notified in advance
      • We will also pour bus foundations and sidewalks in the area surrounding the 21st Ave SW triangle
      • The slip lane opposite 21st Ave SW will remain open to local access only
      • Later this month we will complete asphalt overlay paving in the area
    • Bus stop upgrades in Zone C continue into May
      • Bus stop upgrades at SW Thistle St on the west side of Delridge Way SW rescheduled
        • We will begin demolishing the southwest corner of SW Thistle St this month
        • This work will last for several weeks as we upgrade electrical utilities and rebuild the roadway, curb ramps, and sidewalks in this area
      • Bus stop upgrades at SW Trenton St on the west side of Delridge Way SW continue
        • We will pour the roadway, curb ramps, and sidewalks into next week
    • Upgrades at SW Kenyon St continue
      • The second phase of intersection upgrades at the SW Kenyon St intersection began this week
      • Next week, demolition will move to the southwest corner of this intersection, with electrical installation and paving to follow
      • A uniformed police officer will be stationed at the intersection at all times to help direct traffic
    • Roadwork demolition and paving on the east side between SW Holden St and SW Thistle St
      • Beginning as early as May 10, we will continue demolishing the roadway in front of houses between SW Holden St and SW Thistle St
      • Once the road is demolished, we will upgrade the underground electrical utilities
      • Access to driveways will be maintained with a steel plate
Contact information for local utility providers and services
Seattle Public Utilities 24/7 Emergency Line:
206-386-1800
Seattle Public Utilities - Missed trash collection: Report online
Puget Sound Energy - Gas leak: 1-888-225-5773
Seattle City Light - Report a power outage: 206-684-3000
USPS Westwood Post Office: 206-938-7769
If you have concerns about accessibility or other impacts of construction, please send us your address, contact information, and concerns so that we can better understand and work together throughout construction. You can reach us at DelridgeTransit@Seattle.gov or call 206-775-8739.
Landscapers are continuing to be in and out of this area placing topsoil and upgrading irrigation in the planting strip and roadway median. This work will occur sporadically throughout the workday and will continue into May. Parking will be restricted in this area to allow us to work in the median and to shift traffic around our equipment.
REMINDER: Businesses along the corridor are open during this work. Please follow posted detour signs as you visit these businesses.
At the City of Seattle, we are continuing to follow guidance from federal, state, and local leaders and our public health partners regarding COVID-19. To keep our crews and the public safe, we have required all contractors to submit updated jobsite Health and Safety Plans to ensure that they comply with the safety and social distancing requirements in the Governor’s Order.

Thanks for reading!

Madison Linkenmeyer
Delridge Transit Outreach Team
delridgetransit@seattle.gov
206-775-8739
Copyright © 2020 Seattle Department of Transportation, All rights reserved.

Our mailing address is:
Address: 700 5th Ave, Suite 3800, Seattle, WA, 98104
Mailing Address: PO Box 34996, Seattle, WA, 98124-4996
Phone: 206-684-7623


Want to change how you receive these emails?
You can
update your preferences or unsubscribe from this list.






This email was sent to <<Email Address>>
why did I get this?    unsubscribe from this list    update subscription preferences
RapidRide Expansion Program · 700 5th Ave · Seattle Municipal Tower · Seattle, WA 98104-5058 · USA

Email Marketing Powered by Mailchimp