Upper Site
The RWF team anticipates the Arrowhead Creek trenchless crossing activities through fall 2021. Work includes building and excavating the launch and receiving shafts through spring 2021 and the trenchless pipeline crossing beginning late-April through late-June. This work requires large cranes, excavation equipment, and increased truck traffic.
Installation of new water and sewer utilities in Arrowhead Creek Lane and connections to these new lines to the existing utilities in Brockway Drive has begun and will continue through early summer. These utilities will serve the new electrical building on the upper site. Final paving on Arrowhead Creek Lane and Brockway Drive is anticipated to take place in early May. This work will be noisy.
In the northwest corner of the Upper Site, installation of a large underground vault to hold a large meter and valves began in March and is anticipated to be complete in late spring 2021. This work requires excavation equipment, increased truck traffic, and carpenters to build formwork. Hammering and lumber sawing noises should be expected.
|