Construction Update
Now that groundwork is complete for the season, the focus on site has shifted to putting up the walls.
The installation of walls is progressing quickly, with prefabricated wall assemblies being shipped from the prefab shop daily. The site crew has started with the northwest wing of the building, then will move to the southwest wing, followed by the northeast wing, and finishing with the southeast wing.
Along with the installation of walls, the site crew's focus over the next three weeks is finishing up the crawlspace. Once the walls are up, the site team will prioritize the roof installation.
|