Construction is Still Halted to Address Conflicts with Existing Utilities
Work on the project is still halted due to conflicts with existing gas/telecommunication utilities. The project team is working with utility owners to have these conflicts resolved before our contractor can install the new water and wastewater lines.
It is expected to take about 4 to 5 weeks before the crew will mobilize again to complete the remaining outstanding work. Once we get closer to getting back onsite, we will provide a newsletter update on where the crew will start their work.
If you have questions about this project, please feel free to contact a member of the project team below. We look forward to completing the necessary utility improvements in your neighborhood.