Welcome to the 15th issue of PGCPS Blueprint Schools News and Updates!
 For more information about the program, please visit www.pgcpsblueprintschools.com.
Construction Updates

ADELPHI MIDDLE SCHOOL

Project Executive: Christian Broyles

Past Month’s Accomplishments:
  • Spray fireproofing, installation of exterior metal wall panels, and MEP rough-in at various levels of sector 2K completed.
  • Underground sanitary piping installation at the south connector completed.
  • Curb and gutter installation at the vehicular parking area completed.
  • Drywall close-in on level 1 of sector 1A completed.
  • Building foundation wall waterproofing and backfill at sector 1B completed.
Work In Progress:
  • Site underground storm water piping and grading of parking lot in progress.
  • Spray fireproofing in the connector area in progress.
  • MEPF rough-in in building sectors 1B and 2K, West Commons, and the Gym in progress.
  • Installation of exterior windows and electrical in wall rough-in at sector 1B in progress.
  • Installation of interior door frames on level 1 of sectors 1A and 1B in progress.
30-Day Look Ahead:
  • Interior stud wall framing in sectors 2K and 2G is ongoing.
  • MEP ceiling and wall rough-ins in sectors 1A, 1B, and 2K to continue.
  • Installation of the site underground utilities to continue.
  • Detailing of TPO roof and installation of exterior windows and interior door frames are ongoing.
COLIN L. POWELL K-8 ACADEMY
Project Executive: Arland Knipe

Past Month’s Accomplishments:
  • All remaining concrete slabs on metal deck completed.
  • Secondary steel girt framing at the 4-story tower completed.
  • Spray fireproofing and overhead MEP rough-in on various levels of the 4-story tower completed.
  • In-wall inspections at the kitchen area completed.
  • Curbs, gutters, and sidewalks at the west parking area completed.
Work in Progress:
  • Secondary steel and spray fireproofing in the 3-story tower in progress.
  • TPO Roofing and overhead MEP rough-ins at the 4-story tower in progress.
  • Installation of exterior metal wall panels in building sector 2 in progress.
  • Interior CMU block wall construction at the aux gym, dance, and choir rooms in progress. 
  • Hanging and finishing of drywall in the kitchen areas in progress.
30-Day Look Ahead:
  • Spray fireproofing, interior stud wall framing, and overhead MEP rough-ins on various levels of the 4-story tower to begin and continue.
  • Asphalt paving at the west parking and access road to begin.
  • Installation of exterior metal wall panels to continue
  • Curb and gutter construction at the east parking area to begin.
DREW-FREEMAN MIDDLE SCHOOL

Project Executive:
Christian Broyles
 
Past Month’s Accomplishments:
  • Drywall top out in sector 1B completed.
  • All exterior brick in sectors 1 and 2 completed.
  • Installation of exterior windows in sectors 1A and 1B completed.
  • In-wall blocking and spray fireproofing on various levels of sector 1A completed.
  • Exterior metal wall panels in sector 2K completed.
Work in Progress:
  • Installation of window framing and exterior windows in building sector 2K in progress.
  • Stud wall framing on level 2 of building sector 1A in progress.
  • Ductwork rough-ins in building sectors 1A and 1B in progress.
30-Day Look Ahead:
  • Installation of stairs 1 and 3 is ongoing.
  • Installation of one-side interior drywall in sector 1B to continue.
  • Installation of exterior windows and MEPF rough-ins in building sector 2K is ongoing.
  • Fire sprinkler rough-ins throughout building sector 1 to continue.
HYATTSVILLE MIDDLE SCHOOL
Project Executive: Arland Knipe

Past Month’s Accomplishments:
  • Exterior metal panel installation at sectors 1B and 2G completed.
  • Underground sanitary tie in at Oliver Street completed.
  • Entrance canopy AVB completed.
  • Exterior window installation and caulking and metal ceiling lath installation at sector 2G completed.
  • In-wall MEP rough-ins on various levels of sector 1A completed.
  • Installation of underground grease interceptor at north site completed.
Work in Progress:
  • Trim out of exterior metal panels and gutters and downspouts in sectors 2G and 2K in progress.
  • Drywall one-siding interior walls, interior door frame installation, and electrical power distribution rough-ins in sector 1A in progress.
  • Fire sprinkler installation, electrical in wall rough-ins, and interior stud wall framing and one-siding drywall in sector 1B in progress.
  • Telecom cabling installation in sectors 1A and 1B in progress.
  • Grading and undercutting of the lower parking lot in progress.
  • Underground site utilities  and gas utilities throughout the site in progress.
30-Day Look Ahead:
  • MEP, sprinkler, and telecom overhead rough-in, testing, and insulation is ongoing.
  • Interior paint at back of house spaces to begin.
  • Curb and gutter construction and base asphalt paving at lower lot to begin.
  • Mechanical and electrical room rough-ins to begin.
KENMOOR MIDDLE SCHOOL
Project Executive: Christian Broyles

Past Month’s Accomplishments:
  • Exterior window installation at sector 2K completed.
  • Construction of exterior electrical transformer pad completed.
  • Installation of underground chilled water piping, interior building gas line, and exterior metal panels completed.
  • In-wall MEP rough-ins in sectors 1A and 1B completed.
  • One side drywall in sector 1B completed.
  • All stairs except for main learning stairs completed.
  • Underground sanitary line connection from kitchen to grease interceptor completed.
Work in Progress:
  • Trim, gutters, and downspouts around exterior building perimeter in progress.
  • Overhead ductwork and piping insulation in progress,
  • Electrical room rough-ins in sector 2K in progress.
  • Mechanical room rough-in and final connection to electrical equipment in progress.
  • Interior door frame installation, electrical room buildout, and branch wire pull in sectors 1A and 1B in progress.
  • Low voltage cable rough-ins in sector 1A in progress.
  • Closing interior walls and drywall finishing in sector 1B in progress.
30-Day Look Ahead:
  • Interior wall close-in inspections in sectors 1A and 1B to be completed.
  • Hanging of drywall sector 1A to continue.
  • Overhead electrical rough-ins on level 2 of the building is ongoing. 
  • In-wall electrical rough-ins in sector 2B to continue.
  • Constructions of underground storm lines MH 24, MH 25, and MH 27 to begin.
  • RTU deliveries to site to be completed.
WALKER MILL MIDDLE SCHOOL
Project Executive: Christian Broyles

Past Month’s Accomplishments:
  • Spray fireproofing and in-wall MEP rough ins on various levels of sector 1A completed.
  • One side hanging and in-wall insulation on level 1 of sector 1B completed.
  • Installation of welded door frames, exterior windows, and TPO roofing throughout sector 1 completed.
  • Installation of interior CMU block walls at sector 2G completed.
  • Interior stud wall framing at sector 2K completed.
  • Installation of RTU curbs completed.
Work in Progress:
  • Interior MEP overhead rough-in on level 2 of sector 1A and 1B in progress.
  • Interior stud wall framing in sectors 1A and 2K in progress.
  • Hanging of one side drywall on level 1 of sector 1B in progress.
  • Soil nail retaining wall at back of school site in progress.
  • Installation of stairs 1 and 3 in progress.
  • Underground site utilities in west parking lot in progress.
  • Installation of exterior windows sector 2 in progress.
30-Day Look Ahead:
  • Underground site utilities throughout the project site to continue.
  • Hanging of one side drywall in sector 1A to begin.
  • Installation of soil nail retaining wall to continue.
  • Hanging of second side drywall and drywall finishing for all walls on level 1 of sector 1B to begin.
  • MEP rough-in sector 2K mechanical and electrical rooms to begin.
  • Installation of knock down and welded door frames in sector 1 to begin.
 

*Please note: Construction timeframes shown above are subject to change.

For questions and inquiries on construction in your neighborhood,
please call (301) 317-6199 or email
blueprintschoolsinfo@gilbaneco.com 
Construction Update Meetings


This month, the Blueprint Schools Program held a series of construction update meetings for all six school projects. Each meeting consisted of an overview of the school's statistics and special features, a presentation of the construction schedule moving forward, and a detailed explanation of past, current, and future construction activities. The meeting also provided the communities with the opportunity to ask the project team design and construction related questions during dedicated Q&A sessions at the end of the meetings. The Program plans to hold another round of meetings in the Spring that will include school program and transportation information. In the meantime, if you would like to view the meeting presentations and recordings, visit the project page on the program website at www.pgcpsblueprintschools.com
Know someone else who would like to receive Blueprint Schools
Program News & Updates
? Tell them to sign up
HERE

For more information about the program, please visit www.pgcpsblueprintschools.com






This email was sent to <<Email Address>>
why did I get this?    unsubscribe from this list    update subscription preferences
Brailsford & Dunlavey · 1140 Connecticut Ave NW Ste 400 · Washington, DC 20036-4014 · USA

Email Marketing Powered by Mailchimp