- Monday, October 3rd thru Saturday, October 8th
- Peterson/Ridge Station
- Work Performed
- Frame Ramp #2 Walls – JBCC
- Install Rebar For Ramp #2 – All J Steel
- Pour Ramp 2 Walls = JBCC
- Install Rebar for Ramp 3 Walls – All J Steel
- Structural Repair of Peterson Bridge – American Concrete Restoration
- Sandblast/Paint Peterson Bridge – Era Valdivia
- Location of Work
- East and West Track Side Between N Ridge and West Peterson Ave.
- Southeast Track Side Along N Ravenswood and South of Peterson Ave
- East and West Under Peterson Ave. Bridge
- Public Disruption
- Sidewalk Closure
- Full Closure – 6000 N Ravenswood – 6100 N Ravenswood - CLOSED
- Road Closures
- Northbound 6000 N Ravenswood – 6100 N Ravenswood – CLOSED
- One Lane Closure Eastbound – W Peterson Ave. – CLOSED
- Full Closure Westbound – W Peterson Ave – CLOSED
- Monday, October 3rd thru Saturday, October 8th
- Peterson/Ridge Station
- Work Performed
- Frame Ramp #2 Walls – JBCC
- Install Rebar For Ramp #2 – All J Steel
- Pour Ramp 2 Walls = JBCC
- Frame/Pour Ramp 3 Walls – JBCC
- Install Rebar for Ramp 3 Walls – All J Steel
- Install Rebar for Stair #2 and Abutment Wall – All J Steel
- Structural Repair of Peterson Bridge – American Concrete Restoration
- Sandblast/Paint Peterson Bridge – Era Valdivia
- Install Underpass Lights Under Peterson – JBCC
- Remove Ballast – JBCC
- Bridge Deck Repair – JBCC
- Waterproof Bridge - ACR
- Location of Work
- East and West Track Side Between N Ridge and West Peterson Ave.
- Southeast Track Side Along N Ravenswood and South of Peterson Ave
- East and West Under Peterson Ave. Bridge
- Public Disruption
- Sidewalk Closure
- Full Closure – 6000 N Ravenswood – 6100 N Ravenswood - CLOSED
- Road Closures
- Northbound 6000 N Ravenswood – 6100 N Ravenswood – CLOSED
- One Lane Closure Eastbound – W Peterson Ave. – CLOSED
- Full Closure Westbound – W Peterson Ave – CLOSED
- Ridge Ave Bridge Closure – Saturday-Sunday - CLOSED
If you have additional questions, please email our office at info@40thward.org. Know someone who would like to join our mailing list? Sign up at Metra Ridge/Peterson Station Project.
Yours in Service,

Alderperson Andre Vasquez, 40th Ward
|
|