Construction Projects (No Substantive Changes This Reporting Period)
Town Center:
Phase 2 of the project continues. The contractor is predominantly working on the central parking area and Town Center Drive to the Community Center. They have been asked to and agreed to prioritize these areas in order to re-open Town Center Drive and provide additional parking on the site. The target dates for substantial and final completion have been moved back to April 24, 2023 and May 23, 2023 respectively.
Latest Aerial: YouTube Link
Golf Cart Pathway Expansion (Pierson Road, between Birkdale and Stribling):
This project started on November 14th. The project is ongoing and is approximately 80% complete. We expect this project to be completed by December 23rd. Once completed, the project will include an 8 foot wide pathway section that is capable of hosting golf cart traffic and will enable golf cart users to access Village Park. The public can expect sidewalk closures along Pierson Road for the duration of the project.
Greenview Shores Park Safety Netting:
The contractor was onsite as of December 5th to scope the project and locate the pole locations. We are currently waiting for the contractor to mobilize. Due to labor and supply shortages, the contract was not able to start in December. We have been advised that this project will begin in early 2023. Once completed, the project will provide safety netting along between the softball fields and tennis courts.
Acme Culvert 130 Refurbishment:
This project has been postponed until May 1, 2023 at the request of the Palm Beach Polo POA. Periodic lane closures are expected during the project and will be coordinated with the POA.
Wellington Trace & Primrose Lane Traffic Calming:
This project includes the addition of a Mini Round-a-bout at the intersection of Primrose Lane and Wellington Trace. Construction is anticipated to begin in early 2023. No further updates on this project.
Design Projects
Big Blue Trace Landscaping and Traffic Calming (South Shore Blvd. to Paddock):
This project includes the installation of traffic calming features, landscaping, and irrigation along Big Blue Trace between South Shore Boulevard and Paddock Drive. Design services have been procured with Kimley Horn to complete the landscaping and irrigation construction documents. We anticipate the design work to be completed by March 2023 with the Procurement Phase between April 2023 and June 2023 and Construction Phase between July 2023 and October 2023.
Status: Design phase.
Olympia Park Tennis/Basketball Refurbishment and Pickleball Addition Project:
This project includes resurfacing of the existing tennis and basketball courts. The project will also convert a portion of the existing tennis courts into pickle ball courts. A GMP of $650K was obtained from Burkhardt Construction on November 18th. Since that time we have discussed the possibility of reconfiguring two of the tennis courts and converting to pickle ball courts. A coordination meeting was held with Chuck Gill and Engineering on December 19th to finalize the pickeball court layout. A final GMP was requested by Engineering on December 20th for this project. Procurement phase is expected to continue through February 2023 with Construction Phase in May 2023 to August 2023 (during summer break).
Status: Procurement Phase.
Public Works Storage Building:
This project will facilitate the storage needs for the Public Works Department, with the anticipated demolition of the Old Boys and Girls Club at the South Shore Community Park. The proposed building will be a 10,000sf pre-fabricated structure. The Engineering department is currently working on a performance specification and site plan for the building at the Public Works Facility. The Engineering Department has completed 90% design plans for this effort to date. Design phase anticipated through September 2023 with Procurement/Construction Phase in FY 2024.
Status: Design phase.
Greenbriar Park Restrooms:
This project consists of a new restroom building at the Greenbriar Park Facility. The current facility has reached its useful life and is in disrepair. The current facility is also on septic drainfield facilities. This project will also include permanent sanitary sewer facilities, which the current facility does not have. The Engineering Department has completed 60% design plans for this effort to date. Design phase anticipated through September 2023 with Procurement/Construction Phase in FY 2024.
Status: Design phase.
Greenbriar Park Disc Golf Study:
This project consists of a nine-hole disc (Frisbee) golf facility to be incorporated into Greenbriar Park. The engineering department will be working directly with Jake Hampu, Founder of the Unified Dream Organization to prepare a conceptual disc golf course layout within the open field area of Greenbriar Park.
Status: Conceptual Design Phase/On Hold.
PBSO Existing Building Assessment:
This project consists of the inspection of the current PBSO substation at 14000 Greenbriar Boulevard. The engineering department is preparing a building hardening recommendation and report for this building. The final report is being reviewed by the Village Engineer.
Status: Final Report In Review.
ACME Stormwater Modeling:
Staff is working in coordination with Mock Roos to develop an updated stormwater model, utilizing the latest version of the ICPR (Inter-Connected Pond Routing) software.
Status: Final Report in Review, Due by 12/31/22.
ACME Big Blue Preserve Pump Station:
This project consists of the refurbishment of the pump station for the Big Blue Cypress Preserve. Engineering is coordinating with public works to move the existing pump station into ACME right of way. The pump station currently lies within an easement, outside of the ACME right of way. The project cost is approximately $145,000 and is scheduled to appear before Council in February 2023 for approval. Construction phase anticipated in February-April 2023.
Status: Procurement Phase
C-2 Multi-Purpose Pathway:
This project consist of the construction of a 10ft wide pathway along the C-2 Canal, between Greenview Shores Boulevard and Bent Creek Road. Engineering has received the survey for this project and will commence the design in FY2023. Public Outreach/Design Phase through September 2026; Procurement/Construction Phase in FY 2027.
Status: Design phase.
C-8 Multi-Purpose Pathway (North of Stribling):
This project consists of the construction of a 10ft wide pathway along the C-8 Canal, between Stribling Way and Forest Hill Boulevard. Engineering has received the survey for this project and will commence the design in FY2023. Public Outreach/Design Phase through September 2024; Procurement/Construction Phase in FY 2025.
Status: Design phase.
Greenview Shores Bike Lanes:
This project includes the addition of traffic calming features and bicycle lanes along Greenview Shores Boulevard between Binks Forest Drive and Wellington Trace. Design services are being negotiated with Kimley Horn. We expect to bring the proposals to Council in February for approval. Public Outreach/Design Phase through September 2024; Procurement/Construction Phase in FY 2025.
Status: Design phase.
Greenbriar Boulevard Bike Lanes:
This project includes the addition of traffic calming features and bicycle lanes along Greenbriar Blvd. between Aero Club Drive and Greenview Shores Boulevard. Design services are being negotiated with Kimley Horn. We expect to bring the proposals to Council in February for approval. Public Outreach/Design Phase through September 2024; Procurement/Construction Phase in FY 2025.
Status: Design phase.
Wellington Trace/Big Blue Trace:
This project includes the addition of permissive only left turn lane arrows along the Wellington Trace approaches to Big Blue Trace (N/S). This project also includes the extension of the southbound left turn lane to accommodate the additional vehicle storage needed for the protected turn movement. Engineering is currently working with PBC Traffic to obtain quotes for the placement of permissive only signals at the intersection. Engineering has also prepared a design for the expansion of the existing westbound left turn lane to accommodate the additional queuing that is projected due to the permissive only turn lanes. Design/Coordination Phase through May 2023; Procurement/Construction Phase June 2023-July 2023.
Status: Design phase.
Appaloosa Bridle Trail:
This project consists of drainage improvements for the public Bridle Trail between Appaloosa Trail and Greenbriar Boulevard within the Saddle Trail South Subdivision. Engineering is currently working with Purchasing to utilize Wynn & Sons annual contract for construction of this project. Procurement Phase through April 2023; Construction Phase May 2023-July 2023.
Status: Procurement Phase.
Welcome Sign / Southern Blvd.:
This project consists of adding a “Welcome to Wellington” sign on the NW corner of the Municipal Boundary, which is generally at the Flying Cow/Southern Boulevard intersection. An AT was transmitted on 08/23/2022 regarding the specifics for this project. Engineering is currently working through permitting the sign with FDOT. Permit Phase through April 2023; Construction Phase May 2023 (pending Village Manager approval).
Project Status: Permit Phase
Section 24 Boardwalk Refurbishment:
Engineering is completing design plans for the refurbishment of the boardwalks within Section 24. These plans will be utilized to bid the project in accordance with the federal grant requirements. Staff time has been allocated to complete this task in January 2023. Design/Permit Phase through April 2023; Construction Phase May 2023-July 2023.
Project Status: Design/Permitting Phase
Aero Club Drive Bike Lane Striping:
This project includes adding permanent high visibility striping and signage to the shoulders along Aero Club Drive to convert the recently construction 4 ft road shoulders to official bicycle lanes. Engineering is currently working the the Purchasing Department to utilize an existing Orange County contract to procure the work. Procurement Phase through January 2023; Construction Phase February 2023-March 2023.
ACME R&R C-9 Corridor (FPL Easement) Retention Expansion:
This project consists of excavating and creating large retention areas beneath the FPL powerline easements along the C-9 canal corridor. The intent of the project is to create additional surficial stormwater storage and reduce the overall flood stage within the ACME Improvement District. Surveying services were procured in November and are ongoing. Design service proposals were requested from Engenuity Group in early December. Design/Permit Phase through July 2023; Construction Phase August 2023-October 2023.
Project Status: Design Phase
Traffic Studies/Issues:
Traffic Calming/Vision Zero:
Engineering is coordinating the implementation of Vision Zero Resolution 2022-15 and the Complete Streets Resolution 2022-16. The Village has applied for a "Safe Streets for All" (SS4A) grant for funding to prepare a Village-wide traffic calming study. Once this study has been completed we will begin to apply for grant funds for specific traffic calming projects.
Meadow Wood Traffic Study:
Engineering is currently completing a speed study for the Meadow Wood HOA. We expect the report to be completed by mid-December.
Wellington Trace / Birkdale School Zone Study:
A school zone study was conducted at the intersection of Wellington Trace and Birkdale. It was determined that a school zone is warranted. This will be added to the FY2024 project list.
Permitting
Below is a summary of the departments permitting activity for the week of 11/26/22 - 11/30/22:
- Engineering Permits Applied for: 7
- Engineering Permits Issued: 2
- Inspections Performed: 48
- Reviews Performed: 43
- Fees Collected: $1,337.00
Private Utilities
The Engineering Department continues to monitor construction and assist residents with damage claims as needed. Below is a summary of damage claims to date.
Estimated Damages to Date: $125,000
Recovered Claims to Date: $ 44,000